INSP-Final Inspection | 10/12/2006 | 10/13/2006 | 10/13/2006 | A | PASS |
Forrest France
|
|
|
Required corrections have been made, fire sprinkler permit finaled.
|
INSP-Final Inspection | 10/10/2006 | 10/11/2006 | 10/11/2006 | A | CANC |
Troy Cobbley
|
|
|
No time for inspection due to time constraints and micron plan review
|
INSP-Final Inspection | 10/9/2006 | 10/10/2006 | 10/10/2006 | A | FAIL |
Troy Cobbley
|
|
|
pendant heads in the first floor wormens room are too close. When this is corrected a final will be ok
|
INSP-Sprinkler Rough-in/Hydro | 8/17/2006 | 8/18/2006 | 8/18/2006 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test for the three new system zones passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/15/2006 | 8/16/2006 | 8/16/2006 | A | FAIL |
Forrest France
|
|
|
1st and 2nd floor hydrostatic tests failed due to start pressures well below 200 psi ( 1st floor @190, 2nd floor @160).
|
INSP-Sprinkler Rough-in/Hydro | 8/14/2006 | 8/15/2006 | 8/15/2006 | P | DEFR |
Forrest France
|
|
|
No time to complete inspection today, not all floors are ready for hydro per phone call from contractor, to be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 8/11/2006 | 8/14/2006 | 8/14/2006 | A | CANC |
Forrest France
|
|
|
Leroy stated that this was a hydro but final. His # ###-####. Thanks; Phone #: ###-#### Internet Inspection Request from: Trent Bice Inspection cancelled from web by: Trent Bice
|
INSP-Sprinkler Rough-in | 4/28/2006 | 5/1/2006 | 5/1/2006 | A | PART |
Troy Cobbley
|
|
|
Sprinkler inspection was for main and branchline rough-in only. No piping in the stairwells between columns 1-2 and 10-11 has not been installed or inspected yet. Piping for the most part is ok. The deficiencies have been marked on the city approved plans. The deficiencies include missing retaining straps, overspaced earthquaking, on the first floor riser nipples feeding branchlines where the plans shown supplies from the crosses and on the third floor all of the pipe hangers are attached to the bottom of the open web steel trusses (need engineers approval)
|