INSP-Final Inspection | 4/21/2006 | 4/24/2006 | 4/24/2006 | A | PASS |
Forrest France
|
|
|
Fire sprinkler work passed final inspection.
|
INSP-Sprinkler Rough-in/Hydro | 4/20/2006 | 4/21/2006 | 4/21/2006 | P | PART |
Forrest France
|
|
|
Hydrostatic test for the UG supply and the overhead system both passed inspection. Rough-in inspection is satisfactory as well, need to provide a ball drip at the FDC, and signage at the FDC per review notes.
|
INSP-Supply line flush | 4/12/2006 | 4/13/2006 | 4/13/2006 | A | PART |
Forrest France
|
|
|
UG supply line flush performed satisfactory, the PIV has been adjusted to the required height above finish grade.
|
INSP-Supply line flush | 4/7/2006 | 4/11/2006 | 4/11/2006 | P | DEFR |
Forrest France
|
|
|
No time available to complete this inspection today, to be rescheduled per conversation with contractor.
|
INSP-Sprinkler Rough-in | 3/27/2006 | 3/28/2006 | 3/28/2006 | A | FAIL |
Forrest France
|
|
|
The yard post indicator is below min. height requirements above finish grade, need to cap ductile riser piece, provide seismic clearance at floor slab. Thrust blocks are acceptable, the majority of UG pipe run was covered prior to inspection.
|