INSP-Final Inspection | 11/9/2006 | 11/9/2006 | 11/9/2006 | P | PASS |
Forrest France
|
|
|
Fire sprinkler work is complete, permit finaled.
|
INSP-Final Inspection | 11/6/2006 | 11/7/2006 | 11/7/2006 | P | PART |
Forrest France
|
|
|
Items from previous inspection verified for completion, forward flow completed, okay for final when ball drip and FDC caps are installed.
|
INSP-Final Inspection | 10/25/2006 | 10/26/2006 | 10/26/2006 | A | CANC |
Troy Cobbley
|
|
|
No time for inspection today.
|
INSP-Sprinkler Rough-in/Hydro | 6/6/2006 | 6/7/2006 | 6/7/2006 | A | PART |
Troy Cobbley
|
|
|
Above ground hydro test passed. Sprinkler rough-in failed due to the upright sprinkler heads not meeting NFPA 13 8.6.5.2.1.6 and 8.6.5.2.1.7. Also the sprinkler heads are overspaced at the west end of the sprinkler system.
|
INSP-Sprinkler Rough-in | 4/10/2006 | 4/11/2006 | 4/11/2006 | A | PART |
Troy Cobbley
|
|
|
Canopy is ok to cover but one upright sprinkler head is overspaced from the west end of the central big canopy. See marked plans for exact location.
|
INSP-Sprinkler Rough-in | 4/7/2006 | 4/10/2006 | 4/11/2006 | A | PART |
Troy Cobbley
|
|
|
Canopy is ok to cover but one upright sprinkler head is overspaced from the west end of the central big canopy. See marked plans for exact location.
|
INSP-Sprinkler Rough-in | 4/6/2006 | 4/7/2006 | 4/7/2006 | A | CANC |
Troy Cobbley
|
|
|
Inspection was supposed to be scheduled for monday.
|