Permit Information
Permit NumberFIR06-00068
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 11193 W EMERALD ST
Project NameSPR FRESCA MEXICAN FOODS
Customer Number 
ePlanReview 
Description
FRESCA MEXICAN FOODS (ADDITION) - Fire sprinkler protection is being used for area. To install fire protection in a 26,177-ft/2 two story type III-B addition consisting of wet pipe fire protection in the Production, Maintenance, Equipment, Storage, Offices, and a dry pipe system in the Loading Dock and Dock Office. This work is located on the south and west side of an existing building. Underground fire sprinkler work has been readdressed in this fire permit for underground changes, which was originally permitted under FIR05-00788 (which has not had any inspection recorded to date). First floor 24,875-ft/2 and the second floor is 1,302-ft/2. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD05-02018.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/21/20066/22/20066/22/2006APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection6/20/20066/21/20066/21/2006AFAIL
DetailsTroy Cobbley
Need to do forward flush, repair flow switch on the wet riser, provide inspection tags and hydraulic stickers on the dry riser. Also the review comments need verified for any other items that may be listed.
INSP-Sprinkler Rough-in/Hydro6/15/20066/15/20066/15/2006PPASS
DetailsTroy Cobbley
24 hour air test on the dry system passed.
INSP-Sprinkler Rough-in/Hydro6/14/20066/14/20066/14/2006PPART
DetailsTroy Cobbley
24 hour air test of the dry system started at 12:00 with 44psi showing on the guage
INSP-Sprinkler Rough-in/Hydro6/13/20066/13/20066/13/2006PPASS
DetailsTroy Cobbley
Overhead hydro test for the wet and dry systems passed. This included the FDC as well. Still need to do the 24 hour air test.
INSP-Sprinkler Rough-in6/8/20066/8/20066/8/2006PPASS
DetailsTroy Cobbley
The remaining overhead sprinkler piping is ok for rough-in and the ceiling tile in the office area can be installed. Two heads in the spiral freezer are too close but per the contractor a wall is to be installed between the two. This will need to be verified at the final or next inspection.
INSP-Sprinkler Rough-in5/9/20065/9/20065/9/2006PPART
DetailsTroy Cobbley
Sprinkler rough-in passed for all piping installed south of column line 5. See approved plans for location that two heads need to be added. The spiral freezer is being relocated and has not been piped yet.