INSP-Final Inspection | 6/21/2006 | 6/22/2006 | 6/22/2006 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 6/20/2006 | 6/21/2006 | 6/21/2006 | A | FAIL |
Troy Cobbley
|
|
|
Need to do forward flush, repair flow switch on the wet riser, provide inspection tags and hydraulic stickers on the dry riser. Also the review comments need verified for any other items that may be listed.
|
INSP-Sprinkler Rough-in/Hydro | 6/15/2006 | 6/15/2006 | 6/15/2006 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test on the dry system passed.
|
INSP-Sprinkler Rough-in/Hydro | 6/14/2006 | 6/14/2006 | 6/14/2006 | P | PART |
Troy Cobbley
|
|
|
24 hour air test of the dry system started at 12:00 with 44psi showing on the guage
|
INSP-Sprinkler Rough-in/Hydro | 6/13/2006 | 6/13/2006 | 6/13/2006 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test for the wet and dry systems passed. This included the FDC as well. Still need to do the 24 hour air test.
|
INSP-Sprinkler Rough-in | 6/8/2006 | 6/8/2006 | 6/8/2006 | P | PASS |
Troy Cobbley
|
|
|
The remaining overhead sprinkler piping is ok for rough-in and the ceiling tile in the office area can be installed. Two heads in the spiral freezer are too close but per the contractor a wall is to be installed between the two. This will need to be verified at the final or next inspection.
|
INSP-Sprinkler Rough-in | 5/9/2006 | 5/9/2006 | 5/9/2006 | P | PART |
Troy Cobbley
|
|
|
Sprinkler rough-in passed for all piping installed south of column line 5. See approved plans for location that two heads need to be added. The spiral freezer is being relocated and has not been piped yet.
|