Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR06-00126
StatusFinaled
Name COMMERCIAL FIRE PROTECTION
Site Address 6455 S EISENMAN RD
Project NameSPR UG HARRIS AUTO SALES
Customer Number 
ePlanReview 
Description
HARRIS AUTO SALES FACILITY - To install approximate 150'-0" of 6" C-900 PVC underground starting at the property line on the east side of the proposed structure, off Eisenman Rd., running on the south side of the building and into an unidentified location/room for fire sprinkler protection in a a 6,210-ft/2 two story type V-B (to be fully fire sprinklered) auto sales facility with maintenance shop and wash bay. The 1st floor will be 2,768-ft/2, and the 2nd floor will be 3442-ft/2. Fire sprinklers will be used for story increase. The fire sprinkler underground work shall comply with NFPA 13-2002, NFPA 24-2002 the IFC-2003, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum fire code. This permit is attached to building permit: BLD05-01823.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/24/200610/25/200610/25/2006PPASS
DetailsForrest France
UG fire supply line permit finaled.
INSP-Sprinkler Rough-in/Hydro10/18/200610/18/200610/18/2006PPART
DetailsForrest France
AG hydrostatic test for the FDC piping, antifreeze system, and OH wet system passed, noted missing head at the lower north stair landing.
INSP-Sprinkler Rough-in/Hydro10/11/200610/12/200610/12/2006APART
DetailsForrest France
UG hydrostatic test passed inspection.
INSP-Sprinkler Rough-in/Hydro10/11/200610/11/200610/11/2006PFAIL
DetailsTroy Cobbley
See correction notice for items needing correcting.
INSP-Sprinkler Rough-in/Hydro10/10/200610/11/200610/11/2006ACANC
DetailsTroy Cobbley
Cancel per Terry
INSP-Supply line flush10/10/200610/10/200610/10/2006PPART
DetailsTroy Cobbley
Supply line flush passed. I did a rough-in inspection for the showroom level only and found that the upright sprinkler heads on the west side of the wall that separates the long corridor from the showroom are overspaced. They are 8'-3" off of this wall.
INSP-Supply line flush10/9/200610/9/200610/9/2006PFAIL
DetailsTroy Cobbley
United Water has not turned on the underground supply water yet. Flush not performed
INSP-Sprinkler Rough-in3/1/20063/2/20063/2/2006APART
DetailsForrest France
Inspected thrust block at 90, ductile stub-in, tracer wire, and NRS valve for PI, good for cover at these areas, street connection is not complete at this time, need retaining method at riser flange.
INSP-Sprinkler Rough-in2/22/20062/22/20062/22/2006PPART
DetailsForrest France
UG fire supply line is partially approved for cover. The yard piv, thrust blocks, MJ 90, ductile, tracer wire, and street connections are not completed at this time.