INSP-Final Inspection | 10/24/2006 | 10/25/2006 | 10/25/2006 | P | PASS |
Forrest France
|
|
|
UG fire supply line permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 10/18/2006 | 10/18/2006 | 10/18/2006 | P | PART |
Forrest France
|
|
|
AG hydrostatic test for the FDC piping, antifreeze system, and OH wet system passed, noted missing head at the lower north stair landing.
|
INSP-Sprinkler Rough-in/Hydro | 10/11/2006 | 10/12/2006 | 10/12/2006 | A | PART |
Forrest France
|
|
|
UG hydrostatic test passed inspection.
|
INSP-Sprinkler Rough-in/Hydro | 10/11/2006 | 10/11/2006 | 10/11/2006 | P | FAIL |
Troy Cobbley
|
|
|
See correction notice for items needing correcting.
|
INSP-Sprinkler Rough-in/Hydro | 10/10/2006 | 10/11/2006 | 10/11/2006 | A | CANC |
Troy Cobbley
|
|
|
Cancel per Terry
|
INSP-Supply line flush | 10/10/2006 | 10/10/2006 | 10/10/2006 | P | PART |
Troy Cobbley
|
|
|
Supply line flush passed. I did a rough-in inspection for the showroom level only and found that the upright sprinkler heads on the west side of the wall that separates the long corridor from the showroom are overspaced. They are 8'-3" off of this wall.
|
INSP-Supply line flush | 10/9/2006 | 10/9/2006 | 10/9/2006 | P | FAIL |
Troy Cobbley
|
|
|
United Water has not turned on the underground supply water yet. Flush not performed
|
INSP-Sprinkler Rough-in | 3/1/2006 | 3/2/2006 | 3/2/2006 | A | PART |
Forrest France
|
|
|
Inspected thrust block at 90, ductile stub-in, tracer wire, and NRS valve for PI, good for cover at these areas, street connection is not complete at this time, need retaining method at riser flange.
|
INSP-Sprinkler Rough-in | 2/22/2006 | 2/22/2006 | 2/22/2006 | P | PART |
Forrest France
|
|
|
UG fire supply line is partially approved for cover. The yard piv, thrust blocks, MJ 90, ductile, tracer wire, and street connections are not completed at this time.
|