INSP-Final Inspection | 6/30/2006 | 6/30/2006 | 6/30/2006 | P | PASS |
Forrest France
|
|
|
Final fire sprinkler inspection passed, required corrections have been made, permit finaled.
|
INSP-Final Inspection | 6/29/2006 | 6/29/2006 | 6/29/2006 | P | FAIL |
Forrest France
|
|
|
Need to provide a pressure relief valve for the grid system in the basement per NFPA 13, provide head cages at the exposed upright heads under stairs, one room marked "closet B108" in the basement is missing sprinkler coverage, provide as-builts reflecting actual field install at the first floor lobby where drop ceilings have been deleted and wall layouts changed as previously requested, need to provide playpipe to enable accurate testing of forward flow through the FDC- see review comments. Inspection concluded at this time due to the number of correction items noted as final field inspection is not designed for punch list or quality control purposes on behalf of the contractor.
|
INSP-Final Inspection | 6/28/2006 | 6/28/2006 | 6/28/2006 | P | FAIL |
Forrest France
|
|
|
PIV tamper is adjusted incorrectly, provide "911" sign at the outside bell, the automatic ball drip for the FDC will not function as installed, no other items inspected for final at this time.
|
INSP-Sprinkler Rough-in/Hydro | 6/23/2006 | 6/23/2006 | 6/23/2006 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test of the basement system is satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 6/23/2006 | 6/23/2006 | 6/23/2006 | A | FAIL |
Forrest France
|
|
|
Guage read below 200 psi. at the start of test.
|
INSP-Sprinkler Rough-in/Hydro | 6/21/2006 | 6/22/2006 | 6/22/2006 | A | CANC |
Forrest France
|
|
|
200lb hydro Contact: Steve; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in/Hydro | 6/21/2006 | 6/21/2006 | 6/22/2006 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test for the first floor wet system passed, basement system not ready at this time.
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2006 | 6/21/2006 | 6/21/2006 | A | CANC |
Forrest France
|
|
|
200lb hydro Contact: Steve; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2006 | 6/20/2006 | 6/20/2006 | A | CANC |
Forrest France
|
|
|
200lb hydro UG Contact: Steve ; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Supply line flush | 6/16/2006 | 6/19/2006 | 6/20/2006 | P | PART |
Forrest France
|
|
|
UG supply line flush performed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 6/16/2006 | 6/19/2006 | 6/19/2006 | A | PART |
Forrest France
|
|
|
This inspection was performed on friday afternoon 6/16. Overhead rough-in is acceptable to cover at the drop ceiling areas on the 1st floor. Items needing addressed include one overspaced head in the linen room, one painted head in a restroom, one head blocked by a surface mounted light in the janitors closet, need to provide plans reflecting actual field installation at the lobby area where the drop ceilings were deleted in lieu of OTS. The resubmitted plans are still only issued in a PARTIAL status due to hydraulic calculations per note #3-revise and resubmit for final approval.
|
INSP-Sprinkler Rough-in/Hydro | 5/24/2006 | 5/25/2006 | 5/25/2006 | A | FAIL |
Forrest France
|
|
|
No inspection for cover at the drop ceiling areas performed as requested due to the "partial" approval status of the plans. Contractor to address items 1-3 on plan review notes prior to next field inspection.
|
INSP-Sprinkler Rough-in/Hydro | 5/23/2006 | 5/24/2006 | 5/24/2006 | P | NR |
Forrest France
|
|
|
Not ready for inspection per phone call from contractor.
|
INSP-Sprinkler Rough-in/Hydro | 4/27/2006 | 4/28/2006 | 4/28/2006 | P | PART |
Forrest France
|
|
|
Inspection for cover at the hard lid restrooms in the basement, noted one hanger ring to be changed at an arm over.
|
INSP-Sprinkler Rough-in/Hydro | 4/24/2006 | 4/25/2006 | 4/26/2006 | P | PART |
Forrest France
|
|
|
Completed cover inspection for the 4" feed main inside wall through floor from basement to the 1st floor overhead system, okay to cover as marked on plans.
|
INSP-Sprinkler Rough-in/Hydro | 4/7/2006 | 4/10/2006 | 4/10/2006 | A | PART |
Forrest France
|
|
|
Overhead rough-in is good for cover at the four restrooms with hard lids on the first floor as marked on plans, no other areas requested for inspection at this time.
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2006 | 3/29/2006 | 3/29/2006 | A | PART |
Forrest France
|
|
|
UG fire supply line is good for cover, the target window on the post indicator shall be aligned parallel to the underground pipe per review notes and requirements of IFC 2003.
|