INSP-Final Inspection | 11/8/2006 | 11/8/2006 | 11/8/2006 | P | PASS |
Forrest France
|
|
|
UG fire supply line permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 10/30/2006 | 10/30/2006 | 10/30/2006 | P | CANC |
Troy Cobbley
|
|
|
todd; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Inspection cancelled from web by: Patricia Smith
|
INSP-Sprinkler Rough-in | 9/13/2006 | 9/15/2006 | 9/15/2006 | A | CANC |
Troy Cobbley
|
|
|
Wrong inspection number called in. I spoke with Todd about having the correct permit number called in for the work being inspected.
|
INSP-Sprinkler Rough-in | 9/13/2006 | 9/13/2006 | 9/13/2006 | P | CANC |
Troy Cobbley
|
|
|
todd; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in/Hydro | 9/12/2006 | 9/12/2006 | 9/12/2006 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Supply line flush | 9/1/2006 | 9/5/2006 | 9/5/2006 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in | 6/26/2006 | 6/27/2006 | 6/27/2006 | A | PASS |
Troy Cobbley
|
|
|
Remaining underground supply piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 4/24/2006 | 4/25/2006 | 4/25/2006 | A | PART |
Troy Cobbley
|
|
|
This was a partial inspection of the underground. The 6" supply piping from the riser to the first 45 elbow is ok to cover. Per Dave with DeBest the piping will be at 4'-6" below grade even though it is not now. The grade will need to be atleast 3" above the bottom of the tilt up wall that passes over the piping.
|
INSP-Sprinkler Rough-in/Hydro | 4/18/2006 | 4/19/2006 | 4/19/2006 | A | CANC |
Troy Cobbley
|
|
|
Contact: Dave - Would like UG cover inspection for around 11 -- 11:30 if possible.; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|