INSP-Final Inspection | 6/21/2006 | 6/22/2006 | 6/22/2006 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2006 | 6/21/2006 | 6/21/2006 | A | PART |
Troy Cobbley
|
|
|
Above ground hydro test passed but the forward flush failed.
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2006 | 6/20/2006 | 6/20/2006 | P | CANC |
Troy Cobbley
|
|
|
Wrong permit number called in
|
INSP-Sprinkler Rough-in/Hydro | 6/9/2006 | 6/12/2006 | 6/12/2006 | A | PASS |
Troy Cobbley
|
|
|
sprinkler heads added at the beam obstructions..
|
INSP-Sprinkler Rough-in/Hydro | 6/5/2006 | 6/5/2006 | 6/5/2006 | P | FAIL |
Troy Cobbley
|
|
|
See city approved plans for locations where the upright sprinkler heads are being blocked by steel beams. Additional heads will be required. This inspection was for the overhead shell system piping only and did not include the riser or tenant improvement spaces.
|