INSP-Final Inspection | 9/13/2006 | 9/15/2006 | 9/15/2006 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 8/28/2006 | 8/29/2006 | 8/29/2006 | A | PASS |
Troy Cobbley
|
|
|
The remaining piping on the first floor is ok to cover. Two additional upright sprinkler heads are required as discussed due to duct blockage. Their placement will be verified at the final.
|
INSP-Sprinkler Rough-in/Hydro | 8/24/2006 | 8/25/2006 | 8/25/2006 | P | PART |
Troy Cobbley
|
|
|
The second floor sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 7/24/2006 | 7/24/2006 | 7/24/2006 | P | PASS |
Troy Cobbley
|
|
|
Hydro test of the FDC passed.
|
INSP-Final Inspection | 7/20/2006 | 7/21/2006 | 7/21/2006 | A | FAIL |
Troy Cobbley
|
|
|
Still need to hydro test the FDC and connect/test the alarms. Forward flush passed. The rough-in for the south tenant failed due to numerous obstructions to the upright sprinkler heads by duct work.
|
INSP-Sprinkler Rough-in/Hydro | 7/20/2006 | 7/21/2006 | 7/21/2006 | A | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed. Still need to hydro the remote FDC.
|
INSP-Supply line flush | 6/28/2006 | 6/29/2006 | 6/29/2006 | P | PASS |
Troy Cobbley
|
|
|
underground supply line flushed passed
|
INSP-Sprinkler Rough-in/Hydro | 6/14/2006 | 6/15/2006 | 6/15/2006 | P | PASS |
Troy Cobbley
|
|
|
Piping understairs, above restroom and entry lobby ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 6/14/2006 | 6/16/2006 | 6/14/2006 | P | CANC |
Troy Cobbley
|
|
|
Contact is Jeff Chaney; Phone #: ###-#### Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in/Hydro | 6/12/2006 | 6/12/2006 | 6/13/2006 | P | PASS |
Troy Cobbley
|
|
|
200lb Hydro Test Passed
|
INSP-Sprinkler Rough-in/Hydro | 4/27/2006 | 4/27/2006 | 4/27/2006 | P | PASS |
Troy Cobbley
|
|
|
The remaining portion of the underground is ok to cover
|