INSP-Final Inspection | 6/9/2006 | 6/9/2006 | 6/9/2006 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 6/7/2006 | 6/8/2006 | 6/8/2006 | A | FAIL |
Forrest France
|
|
|
The existing building fire sprinkler system is not yet current with an annual inspection, ceiling tile is missing at several locations, some escutcheons are still missing.
|
INSP-Final Inspection | 6/1/2006 | 6/2/2006 | 6/2/2006 | A | FAIL |
Forrest France
|
|
|
Ceiling tile at several locations is not installed, missing escutcheons at several areas.
|
INSP-Final Inspection | 5/10/2006 | 5/12/2006 | 5/12/2006 | A | PART |
Forrest France
|
|
|
Corrections for the overhead rough-in have been completed, installation is good for cover, final pending cooler construction for dry pendents and ceiling tile/escutcheons at the drop ceiling areas.
|
INSP-Sprinkler Rough-in | 5/5/2006 | 5/8/2006 | 5/8/2006 | A | PART |
Forrest France
|
|
|
Rough-in is good for cover at the restroom and counter soffit hard lid areas only, noted one head is overspaced at the drop ceiling area as marked on approved plans, not all drop ceiling areas are ready for inspection at this time, will require matching response type heads in the same fire area.
|
INSP-Sprinkler Rough-in | 5/5/2006 | 5/5/2006 | 5/7/2006 | P | CANC |
Forrest France
|
|
|
No time to complete inspection, to be rescheduled per conversation with contractor.
|
INSP-Sprinkler Rough-in | 5/1/2006 | 5/2/2006 | 5/1/2006 | P | CANC |
Forrest France
|
|
|
###-#### Mike\\per Mary can not have insp.
|
INSP-Sprinkler Rough-in | 5/3/2006 | 5/3/2006 | | | |
|
|
|
|