INSP-Final Inspection | 9/22/2006 | 9/27/2006 | 9/28/2006 | P | PASS |
Forrest France
|
|
|
Fire sprinkler final inspection passed, permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 9/11/2006 | 9/12/2006 | 9/12/2006 | A | PART |
Forrest France
|
|
|
Re-test of hydrostatic for the underfloor system passed.
|
INSP-Sprinkler Rough-in/Hydro | 9/5/2006 | 9/8/2006 | 9/8/2006 | A | FAIL |
Troy Cobbley
|
|
|
Hydro test failed. Guage appeared to have lost 2-3 psi from 10:15am to 12:15pm.
|
INSP-Sprinkler Rough-in/Hydro | 8/16/2006 | 8/17/2006 | 8/17/2006 | A | PART |
Forrest France
|
|
|
Rough-in for the west underfloor area and OH for the 1st and 2nd levels is acceptable, Hydrostatic test for a portion of these systems at the two 4" main trees and one 3" passed.
|