INSP-Final Inspection | 7/6/2007 | 7/6/2007 | 7/6/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 7/3/2007 | 7/6/2007 | 7/6/2007 | A | CANC |
Troy Cobbley
|
|
|
scotty; Phone #: ###-#### Internet Inspection Request from: Victoria Apatang
|
INSP-Final Inspection | 7/2/2007 | 7/3/2007 | 7/3/2007 | P | FAIL |
Troy Cobbley
|
|
|
The east riser flow switch still did not operate and the company that was to perform the manometer test did not show up.
|
INSP-Alarm Testing | 5/23/2007 | 5/29/2007 | 5/29/2007 | A | FAIL |
Troy Cobbley
|
|
|
See the correction notice for items that did not pass. The spacing of the ceiling mount a/v's are still not code compliant.
|
INSP-Final Inspection | 4/25/2007 | 4/26/2007 | 4/26/2007 | A | FAIL |
Troy Cobbley
|
|
|
I inspected the second floor a/v's for operation. I also inspected the additional strobes added in the storage areas. See the original correction notice for items remaining that need inspection.
|
INSP-Final Inspection | 3/5/2007 | 3/5/2007 | 3/5/2007 | P | FAIL |
Troy Cobbley
|
|
|
We finished testing the duct smoke detectors. One detector located in the 2nd floor break room is mounted in a 90. It will need to be relocated or provide a manometer test. The two tamper switches for both risers did not operate. The PIV tamper did.The west side wet system flow switch operated correctly but the east side inspectors test did not have the correct orfice installed and will need to be retested. To finish project the items listed above need corrected and the notification circuits need to be tested as far as voltage drop and trouble signals as well as device spacing and sound levels. Battery calcs have not been done/verified yet either.
|
INSP-Final Inspection | 3/1/2007 | 3/2/2007 | 3/2/2007 | A | FAIL |
Troy Cobbley
|
|
|
The items tested today were three duct smoke detectors. Mike Timmerman accompanied me on this inspection and verified that additional strobes will be required in the stock rooms due to blockage by the racks. Mike and I also pointed out overspacing of strobes in the retail area.
|
INSP-Final Inspection | 3/1/2007 | 3/1/2007 | 3/1/2007 | P | FAIL |
Troy Cobbley
|
|
|
Items tested today include the phone lines, verified correct panel, interconnection of the six NAC panels to the FACP and tested all manual pull stations.
|
INSP-Alarm Testing | 2/26/2007 | 2/28/2007 | 2/28/2007 | A | FAIL |
Troy Cobbley
|
|
|
The only item tested was the first floor a/v's. Many are overspaced. Strobes are lacking in the corridors formed by the full height racks in the stockrooms. THe racks also form corridors without a/v's within 15' of the ends. Also noted some offices on the second floor that have well over one person in them and not a/v's. No sound levels have been verified yet or end of line voltage drops.
|