INSP-Final Inspection | 11/29/2006 | 11/29/2006 | 11/29/2006 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. I met Mick at a different job site and went over the resubmitted plans.
|
INSP-Final Inspection | 11/16/2006 | 11/16/2006 | 11/16/2006 | P | FAIL |
Troy Cobbley
|
|
|
Still need to address the different sprinkler heads. K factors are different and the anti-freeze solution needs to be verified.
|
INSP-Final Inspection | 11/2/2006 | 11/2/2006 | 11/2/2006 | P | FAIL |
Forrest France
|
|
|
Several items need addressed, left a 6 item c/n on site including heads installed do not match the type system was designed for or submitted on, the single service supply as indicated has not been witnessed for flush see note #11, need to provide access to inspect the OH installation as no rough-in inspection was requested, there is a non-monitored shutoff valve upstream of the system controls and flow switch see note #13 for requirements, the WH closet needs an intermediate head installed, provide verification of the type of antifreeze used as this system is CPVC. NOTE: the sprinkler monitoring has been connected without a fire alarm permit.
|
INSP-Final Inspection | 10/30/2006 | 10/31/2006 | 11/2/2006 | A | CANC |
Forrest France
|
|
|
No time to complete inspection request.
|
INSP-Final Inspection | 10/27/2006 | 10/30/2006 | 10/30/2006 | P | CANC |
Troy Cobbley
|
|
|
mick ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
FIR-Aging Inspection | 10/17/2006 | 10/17/2006 | 10/17/2006 | | NR |
Troy Cobbley
|
|
|
work in progress
|