Permit Information
Permit NumberFIR06-00487
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 8109 W FRANKLIN RD
Project NameSPR CABELA'S T.I.
Customer Number 
ePlanReview 
Description
CABELA'S TENANT IMPROVEMENT * This building is fully fire sprinklered for unlimited area provisions. To modify and add fire sprinkler protection for the interior tenant improvements for a 136,194-ft/2 retail tenant. Fire sprinkler work is related to the installation of a new riser backflow preventer with required forward flow appurtenance, relocate and add upright and pendant heads for added mezzanines, restrooms and diorama's, etc., throughout. System designs were reverified for the added backflow preventer on the systems header, high piled combustible storage, limited height wood pallet and Class IV inrack rack storage. Fire sprinkler work is related to the construction of interior partitions, installation of mezzanines, new restrooms, a small kitchen area and mountain and aquarium fixtures and suspended ceilings. Front canopy construction and dry system modifications were permitted under FIR06-00452. This fire sprinkler work shall comply with IFC 2003, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. Building rack permit is under BLD06-01824. This permit is attached to building permit: BLD06-01174.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/17/20068/17/20068/17/2006PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection8/15/20068/16/20068/16/2006PCANC
DetailsTroy Cobbley
To be rescheduled.
INSP-Sprinkler Rough-in/Hydro8/1/20068/2/20068/2/2006APART
DetailsForrest France
Hydrostatic test for the new rack sprinklers at three areas is satisfactory, items on previous c/n have been verified for completion, added sprinklers at halo above the mountain are acceptable. Need to perform forward flow, test new tampers at the backflow, noted the ball drip at the FDC is leaking.
INSP-Sprinkler Rough-in8/1/20068/1/20068/2/2006PDEFR
DetailsForrest France
Inspection to be completed 8/2
INSP-Sprinkler Rough-in7/27/20067/28/20067/28/2006PPART
DetailsForrest France
OH rough-in inspection for concealed upright heads at entrance to the bargain cave and EC11 head drops in ceiling tile at retail area as marked on plans are okay to cover. Inspection for heads in racks below walkway in the storage area are acceptable except as marked on plan including missing coverage at one area requiring an additional head, heads at two locations are blocked, one head needs to be replaced due to missing liquid in glass bulb, need to install head guards at all locations where uprights are subject to mechanical damage in the racking system.