Permit Information
Permit NumberFIR06-00504
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1112 W MAIN ST
Project NameSPR ROYAL PLAZA (SHELL)
Customer Number 
ePlanReview 
Description
THE ROYAL PLAZA (SHELL) - To install complete fire sprinkler protection consisting of: Underground Fire Service Supply, 750 gpm @ 155 Vertical Turbine Fire Pump with Jockey, Controls and related appurtenance, Floor Zoned Wet systems; Floor Zoned Antifreeze System, Floor Zoned Dry System, Class 1 Automatic Standpipes in each required stair enclosure, Break Tank Supply/Secondary Water Supply system in a new 97,585-ft/2, seven story mix occupancy, shell and core high rise building, constructed of Geopier and concrete foundation, steel structural frame and concrete floors. This building will be fully fire sprinklered. The first floor will have retail, restaurant and parking (8 spaces). The second floor is parking (30 spaces). The third through sixth floor will be residential condominium units. The seventh floor will be individual residential storage units (26 units) an exercise room and a 1300 square foot roof top trellis covered terrace. This is a shell permit only with separate fire permits required for tenant occupancies. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD06-00450. Run 43’ of 6” Ductile iron UG piping from the existing 16” water main located at West Main Street. Stub up into the bldg. through a 6” BFP. Run a 6” supply to the 20,000 gal (Secondary Water Source) tank and pump assembly. From the Booster pump, run a 6” supply to the wet & dry pipe systems serving through out the 7 story mixed use Occupancy bldg. The 6” will also supply a class I standpipe serving each floor. This design is of shell protection only. All fire pump, sprinkler and standpipe work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. The underground fire service supply was installed separately under FIR05-00. This fire permit is attached to building permit: BLD06-00450. This is a shell and core permit only. Separate tenant improvement permits are required to finish this building for occupancy.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/30/200712/3/200712/3/2007APASS
DetailsForrest France
Required corrections have been made, final inspection passed, shell and core fire sprinkler permit finaled.
INSP-Final Inspection11/29/200711/30/200711/30/2007APART
DetailsForrest France
Items on correction notice are complete with the exception of four missing DP heads, need to provide coverage for an open space at the 1st floor or completely enclose as indicated on the building plans to create a non-combustible concealed space, repair the flow switch at the pump discharge manifold, ceiling tiles at some locations are still missing.
INSP-Final Inspection11/28/200711/29/200711/29/2007AFAIL
DetailsForrest France
Red lined areas on approved plan set in need of revision including covered heads, painted heads, missing heads at two locations, incorrect spacing, need to certify the RP and DC valves, perform forward flow, provide signage at floor control vavles, missing ceiling tile and escutcheons at some areas.
INSP-Final Inspection11/27/200711/28/200711/28/2007ANR
DetailsForrest France
INSP-Final Inspection11/26/200711/27/200711/27/2007PCANC
DetailsForrest France
Overbooked
INSP-Final Inspection11/21/200711/26/200711/26/2007APART
DetailsForrest France
Completed sprinkler monitoring testing including the dry system, fire pump, controller and power supplies, noted a QOD is not required on the dry system, missing coverage at the stairs to the basement electrical room, need signage at valves, missing head boxes, finish pack, need to complete forward flow of the BFP, also need to complete a final shell system walkthrough.
INSP-Final Inspection11/20/200711/21/200711/23/2007APART
DetailsForrest France
Begin testing for sprinkler monitoring including tampers and flows at floor control valves, noted one incorrect device address.
INSP-Final Inspection11/19/200711/20/200711/20/2007PNR
DetailsForrest France
INSP-Conference10/26/200710/31/200711/1/2007PPART
DetailsForrest France
Completed preliminary fire pump testing including the required min. manual and automatic starts/stops, churn, rated and peak load testing, and flow testing for comparison to mfg. performance curve data. Generator is not completed to enable testing of the transfer switch at the controler, no fire alarm interconnection or supervision tested at this time due to incomplete FA work.
INSP-Sprinkler Rough-in10/29/200710/30/200710/31/2007PPART
DetailsForrest France
Conclusion of the 24 hr air test for the dry system passed within allowable pressure loss, corrections completed as noted for the common corridors on the 3rd-6th floors.
INSP-Sprinkler Rough-in10/26/200710/29/200710/29/2007PPART
DetailsForrest France
Begin 24 hr. air test for the dry system at 45 psig. at 3:45 pm.
INSP-Sprinkler Rough-in10/25/200710/26/200710/29/2007PFAIL
DetailsForrest France
Duplicated inspection request already completed.
INSP-Sprinkler Rough-in/Hydro10/25/200710/26/200710/29/2007PFAIL
DetailsForrest France
Inspection for the OH rough-in at the common corridors on the 3rd thru 6th floors failed due to overspaced hangers at arm-overs, uprights need to be installed at mech/equip. rooms, incorrect head spacing at the 6th floor, noted sensing lines at the FP and JP are not correct per NFPA 20. The OH hydrostatic test passed.
INSP-Sprinkler Rough-in8/16/20078/17/20078/17/2007APART
DetailsForrest France
1st floor dry system at the NE covered parking area is approved for cover, noted installer to maintain spacing per design not to exceed 120ft sq.
INSP-Sprinkler Rough-in6/11/20076/12/20076/13/2007APART
DetailsForrest France
4th, 5th and 6th floor overhead rough-in inspection passed, missing two seismic braces on the 6th floor, also noted head spacing to be adjusted due to tenant walls.
INSP-Sprinkler Rough-in6/8/20076/11/20076/11/2007APART
DetailsForrest France
OH rough-in for the dry system passed inspection, noted one missing seismic brace at the last piece of 3" main on the 1st floor, OH rough-in for the 3rd floor also completed including terraces, noted some wall changes within the suite spaces which will require some head spacing location mods.
INSP-Sprinkler Rough-in6/7/20076/8/20076/8/2007ACANC
DetailsForrest France
rough in for 2nd - 6th floors Jonathon is the contact Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in4/25/20074/27/20074/27/2007PFAIL
DetailsForrest France
Inspection for the terrace portions of the 3rd and 4th floor failed due to overspaced heads, missing heads and lines which need to be reconfigured as discussed.
INSP-Sprinkler Rough-in2/21/20072/22/20072/22/2007ACANC
DetailsForrest France
This is an overhead rough in for the 3rd and 4th floors. Contact is Jonathon @###-####. Thank You! Phone #: ###-#### Cancel inspection per phone call from contractor.
INSP-Sprinkler Rough-in2/15/20072/15/20072/16/2007PPART
DetailsForrest France
The OH piping hangers and seismic attatchments are okay for cover at the penthouse area only.
INSP-Conference1/11/20071/16/20071/16/2007ADONE
DetailsForrest France
On site conference to discuss fire related HVAC issues.