INSP-Final Inspection | 4/5/2007 | 4/5/2007 | 4/5/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 1/4/2007 | 1/4/2007 | 1/4/2007 | P | PART |
Forrest France
|
|
|
OH hydrostatic test for the new 3" main and new branch lines completed okay.
|
INSP-Sprinkler Rough-in/Hydro | 12/18/2006 | 12/18/2006 | 12/18/2006 | P | PASS |
Troy Cobbley
|
|
|
Hydro test for the canopy passed.
|
INSP-Sprinkler Rough-in/Hydro | 12/14/2006 | 12/14/2006 | 12/14/2006 | P | FAIL |
Troy Cobbley
|
|
|
Hydro test failed. Leaking at heads.
|
INSP-Sprinkler Rough-in | 9/27/2006 | 9/28/2006 | 9/28/2006 | A | PASS |
Troy Cobbley
|
|
|
Additional area of the canopy is ok to cover. See approved plan for location.
|
INSP-Sprinkler Rough-in/Hydro | 9/20/2006 | 9/21/2006 | 9/21/2006 | A | PASS |
Troy Cobbley
|
|
|
This inspection was for the maintenance shop addition. The tie-in, earthquaking and the sidewall head under the overhead door has been finished.
|
INSP-Sprinkler Rough-in/Hydro | 9/19/2006 | 9/19/2006 | 9/19/2006 | P | PASS |
Troy Cobbley
|
|
|
Above ground hydro test and rough-in inspection for the maintenance shop addition is passed.
|
INSP-Sprinkler Rough-in/Hydro | 9/6/2006 | 9/6/2006 | 9/6/2006 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the canopy piping that was inspected.
|