INSP-Final Inspection | 9/29/2006 | 10/2/2006 | 10/2/2006 | A | PASS |
Forrest France
|
|
|
Fire alarm corrections have been verified for completion, inspection passed, permit finaled.
|
INSP-Final Inspection | 9/22/2006 | 9/25/2006 | 9/25/2006 | A | PART |
Forrest France
|
|
|
Need to install a SD and HD at the top of the elevator hoistway per plan, also need to provide as-builts reflecting field modifications. Remaining fire alarm tested satisfactory.
|
INSP-Alarm Testing | 8/17/2006 | 8/17/2006 | 8/17/2006 | P | PART |
Forrest France
|
|
|
Reinspection for c/n items related to the 2nd floor fire alarm tested satisfactory, signals verified. The 1st floor alarm, elevator, updated map, and EOL,s are not completed for inspection at this time.
|
INSP-Alarm Testing | 8/14/2006 | 8/15/2006 | 8/15/2006 | P | FAIL |
Forrest France
|
|
|
Three duct detectors are incorrectly installed, wall mounted av in the electrical room appears to be a ceiling only av, partial test only of the 2nd floor completed today.
|