INSP-Final Inspection | 11/20/2007 | 11/20/2007 | 11/20/2007 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 11/6/2007 | 11/7/2007 | 11/8/2007 | A | PART |
Forrest France
|
|
|
Final pending ceiling tile and escutcheons, noted items from the previous inspection are complete.
|
INSP-Sprinkler Rough-in | 10/16/2007 | 10/17/2007 | 10/17/2007 | A | PART |
Troy Cobbley
|
|
|
This roughin was already done on Tuesday 10-16 under the wrong WPS. The ceiling tile is ok to install. Two rows of pendant sprinklers are blocked by duct work mounted at the ceiling level. The pendants have been installed outside of their listing. No other items except these heads were looked at. I spoke with the building representatives of WPS and we discussed height controls for the racks and moving the existing emergency lights which are at the deck to be below the new ceiling. I advised Forrest of the status.
|
INSP-Conference | 7/16/2007 | 7/17/2007 | 7/17/2007 | A | DONE |
Forrest France
|
|
|
On site visit, discussed with contractor the requirement for the installation to comply with NFPA 13 2002, specifically 12.1.5 (1) regarding sprinkler protection per design for the more demanding area shall extend a min. of 15 ft. beyond its perimeter.
|
FIR-Aging Inspection | 3/8/2007 | 3/8/2007 | 3/12/2007 | | DONE |
Forrest France
|
|
|
Phone call to contractor to determine status, work in progress.
|