Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberFIR06-00660
StatusFinaled
Name VIKING AUTOMATIC SPRINKLER CO
Site Address 4095 S GEKELER LN
Project NameAce Company (Fabrication Build
Customer Number 
ePlanReview 
Description
Ace Company (Fabrication Building) - To install a wet pipe sprinkler system in this newly constructed 9,600 square foot, one story, pre-engineered steel fabrication building. Scope includes a new UG supply and a hydrant within 120'-0" of the FDC. This permit is attached to BLD06-001671.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/24/20071/24/20071/24/2007APASS
DetailsForrest France
Fire sprinkler permit finaled.
INSP-Supply line flush1/23/20071/23/20071/23/2007PFAIL
DetailsTroy Cobbley
forward flush passed but the backflow still needs certified and the alarm interconnections tested.
INSP-Final Inspection1/18/20071/22/20071/22/2007AFAIL
DetailsForrest France
The PIV tamper switch is not installed correctly, contractor to provide means for testing forward flow.
INSP-Sprinkler Rough-in/Hydro1/18/20071/22/20071/22/2007APART
DetailsForrest France
UG fire supply line hydrostatic test passed inspection.
INSP-Final Inspection1/17/20071/19/20071/17/2007PCANC
DetailsForrest France
TYSON - UNDERGROUND INSPECTION; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
INSP-Sprinkler Rough-in/Hydro1/17/20071/19/20071/17/2007ACANC
DetailsForrest France
TYSON - UNDERGROUND INSPECTION; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
INSP-Supply line flush1/4/20071/5/20071/5/2007APART
DetailsForrest France
UG supply line flush completed.
INSP-Sprinkler Rough-in11/22/200611/22/200611/22/2006PFAIL
DetailsForrest France
Need to provide some missing items at the riser including flexible couplings at the top and bottom, psi relief valve per review notes due to grid system, the automatic ball drip for the FDC needs to be relocated to the lowest point for proper operation. The overhead sprinkler rough-in installation is satisfactory.
INSP-Supply line flush10/16/200610/17/200610/17/2006APART
DetailsForrest France
UG fire supply line is acceptable for cover.
INSP-Sprinkler Rough-in10/16/200610/16/200610/16/2006PFAIL
DetailsTroy Cobbley
The bury depth still does not meet the minimum 4'-6" bury.
INSP-Sprinkler Rough-in/Hydro10/12/200610/13/200610/13/2006PFAIL
DetailsForrest France
UG fire supply line does not meet requirements of NFPA 13 for the min. depth of bury. The pipe as installed is approx 10" to 12" too shallow.