Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR06-00698
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 2515 S FIVE MILE RD
Project NameFire Station #14
Customer Number 
ePlanReview 
Description
The scope of work includes 118 lf. of 6" C900 pipe from the property line to a stub up with in the bldg...
Work begins at an existing gate valve located at the property line off of Five Mile.
The fire sprinkler underground work shall comply with NFPA 13-2002, NFPA 24-2002 the IFC-2003, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum fire code. This permit is attached to building permit: BLD06-002046.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/5/20074/6/20074/6/2007APASS
DetailsForrest France
Fire sprinkler permit finaled.
INSP-Final Inspection4/2/20074/3/20074/3/2007AFAIL
DetailsTroy Cobbley
The bypass for the forward flow has been provided but the backflow still needs certified and the 2" clearance around the stub-in needs to be provided.
INSP-Final Inspection3/29/20074/2/20074/2/2007AFAIL
DetailsTroy Cobbley
Need to provide 2" clearance around the stub-in, certify the backflow and provide a permanant bypass for the forward flow. The forward flow passed by just spinning the fdc checkvalve so the forward flush does not need to be redone but the by pass will need to be installed.
INSP-Final Inspection3/26/20073/26/20073/27/2007PCANC
DetailsTroy Cobbley
Per Jonathan the inspection was to be done with the fire alarm inspection. That inspection has not been called in yet
INSP-Sprinkler Rough-in/Hydro3/21/20073/22/20073/22/2007APASS
DetailsTroy Cobbley
Overhead hydro passed.
INSP-Sprinkler Rough-in1/17/20071/19/20071/19/2007PPART
DetailsTroy Cobbley
I inspected the second floor dorm rooms. The upright line located in the peak needs the deflectors positioned horizontal. Also this same line needs to be positioned in the 12" box as detailed in NFPA 13. There is a combustible concealed space that encloses a chimney that will need protection. All of the other lines are ok.
INSP-Supply line flush1/8/20071/9/20071/9/2007PPASS
DetailsTroy Cobbley
Underground flush passed.
INSP-Sprinkler Rough-in/Hydro1/8/20071/9/20071/9/2007APASS
DetailsTroy Cobbley
Underground hydro passed.
FIR-Aging Inspection1/5/20071/5/20071/8/2007 NR
DetailsTroy Cobbley
work is in progress