INSP-Final Inspection | 12/4/2007 | 12/5/2007 | 12/5/2007 | A | PASS |
Forrest France
|
|
|
Fire alarm upgrade completed for this permit.
|
INSP-Final Inspection | 1/26/2007 | 1/26/2007 | 1/26/2007 | P | PART |
Forrest France
|
|
|
Verified elevator voltage monitor and waterflow alarm, permit final pending completion of work scope for the 3rd floor.
|
INSP-Alarm Testing | 1/25/2007 | 1/25/2007 | 1/26/2007 | P | DEFR |
Forrest France
|
|
|
Inspection scheduled for 1/26 as agreed.
|
INSP-Final Inspection | 1/16/2007 | 1/17/2007 | 1/17/2007 | P | FAIL |
Troy Cobbley
|
|
|
I gave Don with Russell Corp. permission to use the phase one area of the third floor. See the building approved plans for the exact location marked and signed by me that was inspected. The items remaining include providing an air balance report for the hood and a K class extinguisher. Only the portion of the phase one area on the third floor alarm was tested. The other area was not complete. The lobby areas of the first and second floor fire alarm was tested. This includes the new facp panel, NAC panel, phone lines and elevator recall. See the approved fire alarm prints for devices marked "ok" that have been tested. Signals have been verified as well. Need 120volt monitoring of the elevator power and the correct orfice in the inspectors test connection. Asbuilts will be required to be submitted to the city prior to final.
|
INSP-Final Inspection | 1/15/2007 | 1/16/2007 | 1/16/2007 | P | CANC |
Forrest France
|
|
|
No time to complete inspection due to high volume of scheduled requests.
|