Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR06-00727
StatusFinaled
Name DELTA FIRE SYSTEMS
Site Address 1455 S CAPITOL BLVD
Project NameSPR-UNG Towne Place Suites
Customer Number 
ePlanReview 
Description
THE TOWNE PLACE SUITES MARRIOTT - To construct a new 72,923 square feet, four story, wood framed, 123 unit motel with approximately 14,838 square feet for support area for meeting rooms, indoor swimming pool and spa, lobby with prep kitchen and 820 square feet of covered entry and patio area. NOTE: This building is required to have a NFPA 13 Fire Sprinkler system used for area increase. This permit does not include the interior swimming pool, spa and related pool equipment. A separate permits with approvals will be required prior to swimming pool construction. All construction per the approved plans and attached comment list. Note: Grading issued under BLD06-01822. Delta Fire services to oversee the installation of the underground fire sprinkler supply piping by utility contractor.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/12/20082/12/20082/12/2008PPASS
DetailsForrest France
UG fire supply line permit finaled.
INSP-Sprinkler Rough-in1/14/20081/14/20081/14/2008PCANC
DetailsForrest France
Wrong permit number called in for inspection.
INSP-Sprinkler Rough-in/Hydro12/5/200712/6/200712/6/2007APART
DetailsForrest France
OH is approved for cover at the drop ceilings on the 2nd, 3rd and 4th floor common corridors only, noted one missing drop and hanger restraint at the 3rd floor corridor-can be verifed at next inspeciton.
INSP-Sprinkler Rough-in/Hydro6/29/20077/3/20077/3/2007APART
DetailsForrest France
OH hydrostatic testing for the attic dry system completed okay, remainder of the dry system rough-in failed due lacking coverage at the east side of the elevator shaft, two uprights at the west end are installed too low, one plugged outlet needs to be rotated to avoid water collection and freeze potential, items from previous inspection have been corrected.
INSP-Sprinkler Rough-in/Hydro6/27/20076/27/20076/27/2007PFAIL
DetailsForrest France
Partial inspection of the dry system for work completed to date as marked on plans, noted overspaced heads at some locations, heads at two areas exceed min.separation, several heads (approx. 35) have been added to cover overbuilds-need to resubmit plans reflecting changes as this work exceeds the scope allowed for field approval.
INSP-Sprinkler Rough-in/Hydro6/20/20076/21/20076/21/2007APART
DetailsForrest France
Hydrostatic tests for the UG supply line, OH wet systems floors 1st, 2nd, 3rd passed inspection.
INSP-Sprinkler Rough-in/Hydro6/19/20076/19/20076/20/2007PPART
DetailsForrest France
OH rough-in is acceptable for the 1st and 2nd floor wet systems, noted field mods on the 1st floor, 2nd floor dead end 1" pipe in the wall to be removed and capped above the ceiling.
INSP-Supply line flush6/12/20076/13/20076/14/2007PPART
DetailsForrest France
Completed UG fire supply line flush.
INSP-Sprinkler Rough-in/Hydro6/12/20076/13/20076/13/2007PPART
DetailsForrest France
4th floor rough-in is acceptable, noted two locations in need of hanger restraints and one pipe in excess of allowed deflection.
INSP-Supply line flush10/2/200610/4/200610/4/2006APART
DetailsTroy Cobbley
Inspection was for cover of the underground pipe. Piping is ok to cover from the building stub-in up to the last 45 elbow. The PIV and the connection to united water has not been completed yet.