INSP-Final Inspection | 12/27/2007 | 12/31/2007 | 12/31/2007 | P | PASS |
Troy Cobbley
|
|
|
Final inspection, under ground flush complete.New set of approved plans with changes made on site. KR
|
INSP-Final Inspection | 10/19/2007 | 10/22/2007 | 10/22/2007 | A | FAIL |
Troy Cobbley
|
|
|
A domestic shutoff valve has been installed that is not shown on the plans or in the hydraulic calculations. Provide revised plans to the city of boise for verification of the changes. The wrong backflow has been installed. Provide heads and as-builts per review note #4. Flush the underground supply. Certify backflow.
|
INSP-Final Inspection | 10/3/2007 | 10/5/2007 | 10/5/2007 | A | CANC |
Troy Cobbley
|
|
|
Brian is the contact, thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus
|
INSP-Final Inspection | 10/1/2007 | 10/3/2007 | 10/3/2007 | A | CANC |
Troy Cobbley
|
|
|
Per Brian there is no access. Permit to be rescheduled
|
INSP-Sprinkler Rough-in | 2/27/2007 | 2/28/2007 | 2/28/2007 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover
|
INSP-Sprinkler Rough-in | 2/26/2007 | 2/27/2007 | 2/27/2007 | A | PART |
Troy Cobbley
|
|
|
Need as-builts and the tenting modified as discussed prior to an ok to cover.
|