INSP-Final Inspection | 6/27/2007 | 6/27/2007 | 6/27/2007 | P | PASS |
Forrest France
|
|
|
Building shell and core fire sprinkler permit finaled.
|
INSP-Final Inspection | 6/5/2007 | 6/6/2007 | 6/6/2007 | A | CANC |
Troy Cobbley
|
|
|
This inspection is being cancelled until forrest is back. Sam rogers contacted the contractor.
|
INSP-Sprinkler Rough-in/Hydro | 5/23/2007 | 5/24/2007 | 5/24/2007 | A | PART |
Forrest France
|
|
|
24 hour air testing of the dry system passed.
|
INSP-Sprinkler Rough-in | 5/22/2007 | 5/23/2007 | 5/23/2007 | A | PART |
Forrest France
|
|
|
Begin 24 hr. air test of the dry system at 9:00am @ 40psi.
|
INSP-Sprinkler Rough-in | 5/21/2007 | 5/22/2007 | 5/22/2007 | A | PART |
Forrest France
|
|
|
Fire pump acceptance testing completed including manual and automatic starts/stops, flow testing, performance curve, pump and jockey controller testing, timed run, phase reversal, and roof top flow test. Mfg. rep to fax field and shop curve data as discussed. Contractor to change out black steel pipe in the sensing lines for non-corrosive as required, also need to separately pipe the relief valve drain to its own termination point. Noted ball vavles for isolation of the jockey pump have been used in place of the recommended gate or butterfly type, sensing line configuration slightly differs from NFPA 20 figures, noted two pluged outlets on the eccentric reducer.
|
INSP-Sprinkler Rough-in | 5/21/2007 | 5/22/2007 | 5/21/2007 | A | CANC |
Forrest France
|
|
|
We are having a pump start up at 8:00am. This is to schedule the start up so you can be there to witness. Mike B is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2007 | 5/21/2007 | 5/21/2007 | P | PART |
Forrest France
|
|
|
OH hydro for the dry system and the retest of the 3rd and 6th floor wet systems tests passed inspection.
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2007 | 5/21/2007 | 5/21/2007 | P | FAIL |
Forrest France
|
|
|
The second same day visit for fire pump testing is not ready for inspection due to leakage at the pump gasket and packing (allowed 25 minutes for contractor to make the necessary repairs which could not be completed while on site), incorrect pump motor rotation, jockey pump rotation not yet verified, concentric and eccentric reducers are installed at the incorrect locations, all sensing line piping shall be non-corrosive, it shall be the contractors responsibility to pre-test the system and it's components prior to scheduling acceptance testing per requirements of NFPA 20.
|
INSP-Sprinkler Rough-in | 5/17/2007 | 5/21/2007 | 5/21/2007 | A | FAIL |
Forrest France
|
|
|
We are having a pump start up at 8:00am. This is to schedule the start up so you can be there to witness. Mike B is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus...........................Contractor replacing a leaking gasket at the pump, noted installation not ready for inspection at the time of requested site visit.
|
INSP-Sprinkler Rough-in/Hydro | 5/15/2007 | 5/16/2007 | 5/16/2007 | P | NR |
Forrest France
|
|
|
Not ready for inspection per conversation with contractor.
|
INSP-Sprinkler Rough-in/Hydro | 4/30/2007 | 5/1/2007 | 5/2/2007 | P | FAIL |
Forrest France
|
|
|
Shell OH wet system hydrostatic test failed due to pressure loss at the guages and visible leakage at the 6th and 3rd floors.
|
INSP-Sprinkler Rough-in | 4/26/2007 | 4/27/2007 | 5/1/2007 | P | PART |
Forrest France
|
|
|
OH rough-in for the penthouse, 6th and 5th floors are approved, noted one overspaced head at the penthouse to be relocated, also checked previous noted defficiencies on the other floors.
|
INSP-Sprinkler Rough-in | 3/20/2007 | 3/23/2007 | 3/23/2007 | A | PART |
Forrest France
|
|
|
OH inspection for the shell system floors 1-4 only, noted some items in need of correction including overspaced heads, seismic bracing, heads blocked by beams, incorrect size hangers, and field modifications to be shown on as-builts, all items noted on approved plan set. Also noted TI wall modifications are currently underway on floors 1 and 2.
|
INSP-Sprinkler Rough-in | 3/19/2007 | 3/20/2007 | 3/21/2007 | P | DEFR |
Forrest France
|
|
|
Inspection rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 3/13/2007 | 3/14/2007 | 3/14/2007 | A | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test passed.
|
INSP-Sprinkler Rough-in/Hydro | 3/13/2007 | 3/13/2007 | 3/13/2007 | P | DEFR |
Forrest France
|
|
|
To be completed 3/14
|
INSP-Supply line flush | 3/13/2007 | 3/13/2007 | 3/13/2007 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed.
|
INSP-Sprinkler Rough-in | 11/16/2006 | 11/17/2006 | 11/17/2006 | A | FAIL |
Forrest France
|
|
|
UG fire supply line pipe does not meet the min. depth of bury as required.
|