INSP-Final Inspection | 10/1/2007 | 10/2/2007 | 10/2/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 9/28/2007 | 9/28/2007 | 10/1/2007 | P | FAIL |
Troy Cobbley
|
|
|
See Ken's field notes on the city approved plans for the items tested.
|
INSP-Alarm Testing | 9/24/2007 | 9/24/2007 | 9/24/2007 | P | FAIL |
Troy Cobbley
|
|
|
The fire alarm panel, after testing between two to six room detectors will automatically silence the sounder bases. I do not know if the panel silences all building alarms. Also the data from one of the tenant rooms is being corrupted by the time it is received at the facp and is causing "wave form" errors at the facp. I spoke to the Pyrotronics technical support and they believe that the silencing problem could be a logic/programming issue. They need to view the program to tell. I stopped the inspection out of concerns that if it is a hardware issue all of the items tested would have to be retested when a new panel is installed. Just to make a note when the main fire alarm panel is reset it takes nearly 7 minutes to return to normal. It also takes around 15 seconds to activate the sounder bases in the rooms. I was told this is due to the size of the system and a slow processor in the fire alarm panel. I spoke to Sam Rogers about these concerns. This entry has been made under this permit only due to none access to the other permits because of their being in the "review status"
|
INSP-Alarm Testing | 9/18/2007 | 9/21/2007 | 9/21/2007 | A | DONE |
Troy Cobbley
|
|
|
See the city approved plans for locations tested by Ken.
|
INSP-Alarm Testing | 9/18/2007 | 9/20/2007 | 9/20/2007 | A | CANC |
Troy Cobbley
|
|
|
Overbooked with Micron plan review.
|
INSP-Alarm Testing | 9/18/2007 | 9/19/2007 | 9/19/2007 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection was actually a conference with the fire alarm designer. Mike Timmerman and I went over the a/v and smoke detector deficiencies with him. Mike is allowing him to red line the resubmittals that are waiting in line at the city for review.
|
INSP-Alarm Testing | 9/17/2007 | 9/18/2007 | 9/18/2007 | A | DONE |
Troy Cobbley
|
|
|
No actual inspection was perform today do to multiple problems found.They include the fire alarm panel does not sound on second alarm. There are many over spaced detectors in lounge area. There are areas where smoke detectors and a/v's need to be added. In the dining areas the cieling mounts a/v'sare know mounted on the walls. The kithen area has same problems as well. The contractor needs to resubmit these changes.
|
INSP-Alarm Testing | 9/17/2007 | 9/17/2007 | 9/17/2007 | A | FAIL |
Troy Cobbley
|
|
|
The dialer was in trouble and would not clear. No test performed.
|
INSP-Alarm Testing | 9/13/2007 | 9/14/2007 | 9/14/2007 | A | DONE |
Troy Cobbley
|
|
|
See the city approved plans for devices tested in area D.
|
INSP-Alarm Testing | 9/13/2007 | 9/13/2007 | 9/13/2007 | A | CANC |
Troy Cobbley
|
|
|
Overbooked
|
INSP-Final Inspection | 8/31/2007 | 9/4/2007 | 9/4/2007 | A | CANC |
Troy Cobbley
|
|
|
No alarm inspection performed today. Just sprinklers were looked at.
|