INSP-Final Inspection | 10/1/2007 | 10/2/2007 | 10/2/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 9/28/2007 | 10/1/2007 | 10/1/2007 | A | FAIL |
Troy Cobbley
|
|
|
See Ken's notes on the city approved plans for items tested and deficiencies found.
|
INSP-Alarm Testing | 9/12/2007 | 9/12/2007 | 9/13/2007 | P | DONE |
Troy Cobbley
|
|
|
The fire alarm panel manufacturer, phone lines and supervision of NAC 4 and NAC 5 were verified. The smoke detector in the facp room and down the corridor as marked on the plans were tested. I found that the smoke detector and audio/visual were both overspaced from the end of the corridor. Also a NAC panel has been added in the facp room. Plans need to be resubmitted showing the new NAC. The facp was in trouble due to missing monitor modules at the roof top units. I went over requirements with the owner, building contractor, electrical contractor and fire alarm contractor.
|
INSP-Final Inspection | 8/31/2007 | 9/4/2007 | 9/4/2007 | A | CANC |
Troy Cobbley
|
|
|
No alarm inspection performed today. Just sprinklers were looked at.
|
INSP-Conference | 8/29/2007 | 8/31/2007 | 8/31/2007 | A | DONE |
Troy Cobbley
|
|
|
The fire alarm contractor wanted to know the specifics of why I can't dedicate specific times to show up and spend doing their inspection.
|