INSP-Final Inspection | 2/1/2007 | 2/2/2007 | 2/2/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 2/1/2007 | 2/1/2007 | 2/1/2007 | P | FAIL |
Troy Cobbley
|
|
|
Need to test interconnection with the fire alarm system prior to finaling.
|
INSP-Sprinkler Rough-in/Hydro | 1/22/2007 | 1/23/2007 | 1/23/2007 | A | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 1/22/2007 | 1/22/2007 | 1/22/2007 | P | FAIL |
Troy Cobbley
|
|
|
Hydro test failed
|
INSP-Supply line flush | 1/8/2007 | 1/8/2007 | 1/8/2007 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in | 12/11/2006 | 12/11/2006 | 12/11/2006 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover.
|
INSP-Sprinkler Rough-in/Hydro | 12/8/2006 | 12/8/2006 | 12/8/2006 | P | FAIL |
Troy Cobbley
|
|
|
Tenting of the sprinkler piping still is not acceptable. I went over the problem areas with the superintendant
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2006 | 12/4/2006 | 12/4/2006 | A | FAIL |
Troy Cobbley
|
|
|
Tenting for the sprinkler piping was not adequate. There are many locations with limited or no tenting. I left a sticker to not cover the sprinkler piping on window.
|
INSP-Sprinkler Rough-in/Hydro | 11/27/2006 | 11/27/2006 | 11/27/2006 | A | PART |
Troy Cobbley
|
|
|
Sprinkler piping rough-in passed. Several heads do do meet the spacing requirements from the wall mounted supply diffusers. Per tom and I's discussion he will provide an intermerdiate temp head. Piping cannot be covered until a tenting inspection has been performed.
|