Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR06-00844
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 10136 S FEDERAL WAY
Project NameMICRON NANOFAB
Customer Number 
ePlanReview 
Description
(MICRON NANOFAB)(GRADING & DRAINAGE) To perform grading and drainage on the site, and install underground utilities to prepare for future fabrication facility to be constructed under separate permits. *JCB* Shiloh Fire Protection to install 252 LF of 8" C-900 to supply fire sprinker system. Also installing 217 LF of 4" C-900 from riser room back to FDC located at sidewalk.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/13/200711/14/200711/14/2007APASS
DetailsForrest France
UG fire supply line permit finaled.
INSP-Final Inspection11/12/200711/13/200711/13/2007PCANC
DetailsForrest France
Mike B is the contact, thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus
INSP-Sprinkler Rough-in/Hydro6/15/20076/18/20076/19/2007PPART
DetailsForrest France
UG fire supply line flush completed satisfactory.
INSP-Supply line flush6/15/20076/18/20076/18/2007PPART
DetailsForrest France
UG fire supply line hydrostatic test passed.
INSP-Sprinkler Rough-in3/6/20073/7/20073/7/2007APASS
DetailsTroy Cobbley
The underground supply and remote FDC piping from the last 90 to the inside of the building is ok for cover. Link seal was installed.
INSP-Sprinkler Rough-in3/5/20073/5/20073/5/2007PPART
DetailsForrest France
UG fire supply line and remote FDC UG piping are good for cover from the point of connection at the street to just prior to the last 90 at the building, will need to verifiy last piece of 4" FDC piping, link seals, and thrust blocking at the 90's which are not yet completed at this time.