INSP-Final Inspection | 3/22/2007 | 3/22/2007 | 3/23/2007 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 3/19/2007 | 3/19/2007 | 3/19/2007 | P | PART |
Troy Cobbley
|
|
|
Hydro test for the pre-action system passed. Hangers have been attached to the bottom chord of the trusses. An engineer needs to sign off on this or the hanger need to go to the top chord.
|
INSP-Sprinkler Rough-in/Hydro | 3/12/2007 | 3/12/2007 | 3/12/2007 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled per Rick
|
INSP-Sprinkler Rough-in/Hydro | 3/8/2007 | 3/8/2007 | 3/9/2007 | P | FAIL |
Troy Cobbley
|
|
|
Hydro test for the pre-action room failed
|
INSP-Sprinkler Rough-in/Hydro | 3/1/2007 | 3/2/2007 | 3/2/2007 | A | FAIL |
Troy Cobbley
|
|
|
Above ground hydro test failed.
|
INSP-Sprinkler Rough-in | 2/6/2007 | 2/6/2007 | 2/6/2007 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was for just the office areas not the pre-action area. The office areas can not be covered yet due to insulation falling from the deck and creating obstructions to the upright sprinkler heads. Also an upright needs to be added in the west restroom due to an overspacing issue. The plans need to be resubmitted to the city for approval due to the amount of additional upright heads on the pre-action system. Many of these heads are in the hydraulic remote area.
|
INSP-Conference | 12/28/2006 | 12/29/2006 | 12/29/2006 | A | DONE |
Troy Cobbley
|
|
|
Contractor will have to attach earthquake bracing to the top of the trusses, they will have to resubmit if the change the supply to the preaction system and the duct can not be treated as obstructed construction. No approved plans were on site for review.
|