INSP-Final Inspection | 2/13/2008 | 2/13/2008 | 2/13/2008 | P | PASS |
Forrest France
|
|
|
C/N items are finished, fire sprinkler permit finaled.
|
INSP-Final Inspection | 2/11/2008 | 2/12/2008 | 2/12/2008 | A | FAIL |
Forrest France
|
|
|
Need to remove travel caps and install escutcheons at each sprinkler head in the mechanical closets per unit.
|
INSP-Final Inspection | 2/6/2008 | 2/7/2008 | 2/7/2008 | P | FAIL |
Forrest France
|
|
|
Missing several items for final at the riser similar to the adjacent building #2. Not ready for final due to missing and defficient items.
|
INSP-Sprinkler Rough-in/Hydro | 5/11/2007 | 5/14/2007 | 5/14/2007 | P | PART |
Forrest France
|
|
|
OH hydrostatic test for the west building (bld#1) passed.
|
INSP-Sprinkler Rough-in/Hydro | 3/30/2007 | 4/3/2007 | 4/3/2007 | A | PART |
Forrest France
|
|
|
OH rough-in inspection completed for building one, noted some areas in need of correction prior to approval for cover including two heads too close to adjacent walls, heads at two locations that exceed min. spacing requirements, tenting at one head 2nd floor mech. closet is inadequate, need to provide proper coverage at the garage soffits above the water heaters.
|
INSP-Sprinkler Rough-in/Hydro | 1/24/2007 | 1/25/2007 | 1/25/2007 | A | PART |
Forrest France
|
|
|
UG supply line is approved for cover.
|