INSP-Final Inspection | 2/21/2008 | 2/22/2008 | 2/22/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Forward flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/18/2007 | 10/19/2007 | 10/19/2007 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test passed
|
INSP-Sprinkler Rough-in | 10/17/2007 | 10/18/2007 | 10/18/2007 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test started at 8:00 with 41 1/4 lbs
|
INSP-Sprinkler Rough-in/Hydro | 10/16/2007 | 10/17/2007 | 10/17/2007 | A | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed.
|
INSP-Supply line flush | 9/27/2007 | 9/28/2007 | 9/28/2007 | A | PASS |
Troy Cobbley
|
|
|
The underground supply line flush for the building is passed. I also gave a rough-in inspection for the overhead piping that Forrest had not looked at. This piping is ok.
|
INSP-Sprinkler Rough-in/Hydro | 9/20/2007 | 9/21/2007 | 9/21/2007 | A | PASS |
Troy Cobbley
|
|
|
The underground flush for the future supply, located to the west of the new building has passed.
|
INSP-Supply line flush | 9/19/2007 | 9/20/2007 | 9/20/2007 | A | FAIL |
Troy Cobbley
|
|
|
Arrived at the job site but the contractor was not there. Needs to be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 9/12/2007 | 9/12/2007 | 9/12/2007 | P | PASS |
Troy Cobbley
|
|
|
The underground hydro test passed for both lines.
|
INSP-Sprinkler Rough-in/Hydro | 9/10/2007 | 9/10/2007 | 9/11/2007 | P | FAIL |
Troy Cobbley
|
|
|
The underground supply line blew a seal and will need to be dug up and repaired.
|
INSP-Sprinkler Rough-in | 5/23/2007 | 5/24/2007 | 5/24/2007 | P | PART |
Forrest France
|
|
|
UG fire supply line install matches approved plans-okay to bury, also inspected three rooms with hard lid ceilings as circled and initialed on stamped plans okay for cover.
|
INSP-Sprinkler Rough-in | 3/21/2007 | 3/22/2007 | 3/22/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground stub-in only is ok to bury.
|