INSP-Final Inspection | 2/15/2007 | 2/15/2007 | 2/15/2007 | P | PASS |
Forrest France
|
|
|
Final fire sprinkler inspection passed, permit finaled.
|
INSP-Final Inspection | 2/6/2007 | 2/7/2007 | 2/7/2007 | A | FAIL |
Troy Cobbley
|
|
|
Ceiling tile is not installed and the approved plans are still not on site.
|
INSP-Final Inspection | 2/6/2007 | 2/6/2007 | 2/6/2007 | P | FAIL |
Troy Cobbley
|
|
|
Need ceiling tile installed and approved plans on site for me to verify that what is should be.
|
INSP-Sprinkler Rough-in/Hydro | 1/29/2007 | 1/30/2007 | 1/30/2007 | A | PART |
Forrest France
|
|
|
Required corrections have been verified, OH rough-in approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 1/26/2007 | 1/29/2007 | 1/29/2007 | P | NR |
Forrest France
|
|
|
Required work is not yet complete for inspection.
|
INSP-Sprinkler Rough-in/Hydro | 1/25/2007 | 1/26/2007 | 1/26/2007 | A | FAIL |
Forrest France
|
|
|
Noted locations on approved plan set which are in need of revision including missing head placement and obstructed heads.
|
INSP-Sprinkler Rough-in/Hydro | 1/24/2007 | 1/24/2007 | 1/26/2007 | P | DEFR |
Forrest France
|
|
|
Inspection to be completed as scheduled on 1/26.
|