Permit NumberFIR07-00031
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1112 W MAIN ST Unit: 401
Project NameROYAL PLAZA
Customer Number 
ePlanReview 
Description
This TI in suite #401 includes dropping 15 residential heads into the new wall and ceiling layout of the dwelling unit and 2 other Dry SSP heads on the terrace. The work shall be performed in accordance with NFPA13R installation guidelines. This building is fully fire sprinklered for one-hour substitution. The fire sprinkler system work shall comply with IFC 2003, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD6-03313.
When tenant work affects fire sprinkler protection outside the permitted work area due to the installation of tenant-demising or new partition walls, the affected area sprinkler coverage outside the BLD permit will fall under the Fire Permit scope of work, to maintain the required fire protection within the fire sprinklered facility. The "Riser" and its supplies which include all appurtenances (including tamper, alarm and alarm monitoring) relating to the normal and correct function and integrity of this system will fall under the jurisdiction for code compliant verification.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/6/200712/6/200712/6/2007PPASS
DetailsForrest France
Accepted as-built plans, permit finaled.
INSP-Final Inspection12/5/200712/5/200712/5/2007PFAIL
DetailsForrest France
Contractor needs to provide two copies of as-built plans.
INSP-Final Inspection11/30/200712/3/200712/3/2007AFAIL
DetailsForrest France
Approved plans were not on site at the time of inspection, also need to provide as-builts for field modifications.
INSP-Sprinkler Rough-in10/29/200710/30/200710/31/2007PDEFR
DetailsForrest France
See inspection notes under the shell permit.
INSP-Sprinkler Rough-in/Hydro10/25/200710/26/200710/29/2007PPART
DetailsForrest France
Hydro test passed.
INSP-Sprinkler Rough-in8/16/20078/17/20078/17/2007ANR
DetailsForrest France
Pending light fixture obstruction issues.
FIR-Aging Inspection7/23/20077/23/20077/24/2007 DONE
DetailsForrest France
Work in progress.