INSP-Sprinkler Rough-in/Hydro | 3/23/2007 | 3/26/2007 | 3/26/2007 | A | PART |
Forrest France
|
|
|
Verified insulation install at ceiling pockets, OH rough-in is good for cover.
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2007 | 2/28/2007 | 2/28/2007 | A | PART |
Forrest France
|
|
|
OH rough-in installation is acceptable, provide as-built plans for field modifications to pipe routing, need to verifiy non-sprinklered combustible cavities are completely filled with insulation for allowance of the exception per NFPA 13 prior to OH cover.
|
INSP-Sprinkler Rough-in/Hydro | 2/22/2007 | 2/23/2007 | 2/23/2007 | A | PART |
Forrest France
|
|
|
Inspection for OH cover at unit G5 only, shell and core plans marked for area inspected, noted pendent heads at some locations are in close proximity to electrical junction boxes and may present an obstruction depending on the type of light fixture installed, also noted field modifications which need to be shown on as-built plans.
|
INSP-Sprinkler Rough-in/Hydro | 2/21/2007 | 2/22/2007 | 2/22/2007 | P | DEFR |
Forrest France
|
|
|
Inspection rescheduled per discussion with contractor.
|