Permit Information
Permit NumberFIR07-00100
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 3046 S BOWN WAY
Project NameRIVERIDGE OFFICE
Customer Number 
ePlanReview 
Description
Fully sprinkle a new two story structure including the overbuild entryway. The system will be controlled from the riser room located on the West side of the bldg. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD06-02369. This permit is also attached to permit FIR06-00897 for Underground work.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/30/20074/30/20074/30/2007PPASS
DetailsForrest France
Corrections are complete, fire sprinkler permit finaled.
INSP-Final Inspection4/19/20074/20/20074/20/2007AFAIL
DetailsForrest France
Provide an outside control valve as indicated on fire code review notes, also need to repair one escutcheon at the second floor atrium.
INSP-Sprinkler Rough-in/Hydro4/19/20074/19/20074/19/2007PPART
DetailsForrest France
OH hydrostatic retest of the wet and antifreeze systems passed.
INSP-Final Inspection4/17/20074/18/20074/18/2007PFAIL
DetailsTroy Cobbley
Need drawings resubmitted as previously requested. Still need the hydro test performed. Also since the anti-freeze connection point has been relocated an additional flow switch is required.
INSP-Sprinkler Rough-in/Hydro3/28/20073/30/20073/30/2007ADEFR
DetailsForrest France
This is just an overhead hydro. Contact is Brian D. @ ###-####. Thank you. Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro3/22/20073/27/20073/27/2007PFAIL
DetailsForrest France
OH hydrostatic test failed due to pressure loss at the guage and visible leakage at system piping, still need to provide resubmittals for changes in overhead piping.
INSP-Sprinkler Rough-in/Hydro2/26/20072/27/20072/27/2007ANR
DetailsForrest France
Corrections are not yet complete for re-inspection.
INSP-Sprinkler Rough-in/Hydro2/23/20072/26/20072/26/2007PPART
DetailsForrest France
UG hydrostatic test completed satisfactory.
INSP-Sprinkler Rough-in2/23/20072/26/20072/26/2007PFAIL
DetailsForrest France
The installation does not match plan (mains re-routed, antifreeze supply point moved, heads deleted, DSW heads added, branch lines moved, etc.), 1st floor has overspaced and blocked heads at several locations, SW heads installed too low, 2nd floor has overspaced uprights, mixed temp. heads in the same fire area, blocked upright at the atrium, antifreeze install does not match plan, will require plan resubmittal reflecting actual installation.
INSP-Supply line flush2/23/20072/26/20072/26/2007PNR
DetailsForrest France
Contact is Perly @ ###-####.
Thank you Phone #: ###-####