INSP-Final Inspection | 5/18/2007 | 5/21/2007 | 5/21/2007 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work is approved for final, noted signage at the backflow to be installed as discussed and verified at BLD final.
|
INSP-Sprinkler Rough-in | 2/20/2007 | 2/20/2007 | 2/20/2007 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping as installed is ok but I requested a tenting inspection prior to covering the piping. Mike is getting with the contractor to set it up next week.
|