INSP-Final Inspection | 10/23/2007 | 10/24/2007 | 10/24/2007 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/17/2007 | 10/23/2007 | 10/23/2007 | A | FAIL |
Troy Cobbley
|
|
|
One room needs the institutional heads installed, forward flush needs to be performed and a general final walk through.
|
INSP-Sprinkler Rough-in/Hydro | 10/15/2007 | 10/17/2007 | 10/17/2007 | P | PASS |
Troy Cobbley
|
|
|
The hydro test for the header and fdc and the preaction system passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/11/2007 | 10/15/2007 | 10/15/2007 | A | PART |
Troy Cobbley
|
|
|
OH Hydro Inspection on the three wet risers passed. The preaction hydro test failed. The riser/header and fdc still needs to be hydro tested.
|
INSP-Sprinkler Rough-in | 9/20/2007 | 9/21/2007 | 9/21/2007 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping above the layin ceiling tile areas are ok to cover.
|
INSP-Sprinkler Rough-in | 9/19/2007 | 9/20/2007 | 9/20/2007 | P | CANC |
Troy Cobbley
|
|
|
OH Cover Inspection
Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley Inspection cancelled from web by: Alicia Pauley
|
INSP-Sprinkler Rough-in | 8/20/2007 | 8/22/2007 | 8/22/2007 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for location where the sprinkler piping is ok to cover
|
INSP-Sprinkler Rough-in/Hydro | 8/20/2007 | 8/22/2007 | 8/22/2007 | P | PASS |
Troy Cobbley
|
|
|
UG Hydro Test and flush passed
|
INSP-Sprinkler Rough-in | 8/15/2007 | 8/17/2007 | 8/17/2007 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where the spirnkler piping is ok to cover. Ceilings will need to be added in the mechanical closets or the walls will need to extend to the deck. The upright will not suffice. A separation is needed between the sprinklered area and the non-sprinklered area
|
INSP-Sprinkler Rough-in | 7/26/2007 | 7/31/2007 | 7/31/2007 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the areas of the medical wing that the rough-in piping is passed and other areas where the piping is ok to cover. I found one retaining strap missing and one drop that was positioned as a sprig up.
|
INSP-Sprinkler Rough-in/Hydro | 3/27/2007 | 3/28/2007 | 3/28/2007 | A | PART |
Forrest France
|
|
|
The UG fire supply line stub-in and IBR are approved for cover.
|