Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR07-00204
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 815 E PARK BLVD
Project NameFALCON BLDG
Customer Number 
ePlanReview 
Description
Beginning at the 8” loop in the North parking lot, install + or – 160” of 6” C-900 underground service leading into the riser room. A wet pipe sprinkler system will serve through out the bldg. The South Atrium & Vestibule at the main entryway will be protected by an auxiliary anti-freeze system.
The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD06-01784.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/29/200710/29/200710/29/2007PPASS
DetailsForrest France
Fire sprinkler final inspection passed per site visit completed by K. Roule, permit finaled.
INSP-Sprinkler Rough-in/Hydro9/21/20079/21/20079/21/2007PPART
DetailsForrest France
Retest of the overhead hydrostatic for the 3rd floor wet system passed.
INSP-Sprinkler Rough-in/Hydro8/31/20079/4/20079/4/2007APART
DetailsForrest France
Hydrostatic testing for the first and second floors passed, the third floor hydro failed due to pressure loss at the guage.
INSP-Sprinkler Rough-in/Hydro8/30/20078/31/20078/31/2007APART
DetailsForrest France
The east and west standpipes and the antifreeze system all passed hydrostatic testing. Floors 1, 2 and 3 failed hydrostatic test due to visible leakage and pressure loss below 200 psi at the guages.
INSP-Sprinkler Rough-in8/21/20078/22/20078/22/2007APART
DetailsForrest France
Overhead install at the drop ceilings for the core areas on the 3rd, 2nd and 1st floors are approved for cover.
INSP-Sprinkler Rough-in7/5/20077/9/20077/9/2007APASS
DetailsTroy Cobbley
The rough-in for the first floor is ok except for the sprinkler upright in the northwest corner, as marked on the plans, that is overspaced by being 7'10" off of the wall. Also there is no separation of nonsprinklered areas from the sprinklered areas as per NFPA 13 Chapter 8. I spoke to the general contractor Nick about this. It appears that he is going to install the separation instead of installing additional upright sprinklers. This will ave to be verified at the final.
INSP-Sprinkler Rough-in7/5/20077/6/20077/5/2007ADEFR
DetailsForrest France
Inspection rescheduled for 7/9
INSP-Sprinkler Rough-in7/2/20077/2/20077/2/2007PPART
DetailsForrest France
Rough-in inspection for the 2nd and 3rd floors completed, noted two heads exceed min. separation unless sheetrock is extended to the deck, ssu at the west stair landing does not meet req. distance from the deck, east stairway heads have not been installed at this time, noted field modifications for the 1st floor antifreeze loop to be indicated on as-built drawings, missing seismic bracing on the south antifreeze system main.
INSP-Sprinkler Rough-in6/15/20076/18/20076/18/2007APART
DetailsForrest France
Hard lid ceilings at the north entry atrium including soffits and dry sidewalls are okay for cover as noted on approved plans sheet FP3 2nd floor.
INSP-Sprinkler Rough-in6/7/20076/8/20076/8/2007APASS
DetailsTroy Cobbley
See the city approved plans with todays date for the locations where the piping above the hardlids is ok to cover.
INSP-Supply line flush6/6/20076/7/20076/7/2007APASS
DetailsTroy Cobbley
Underground flush passed
INSP-Sprinkler Rough-in5/29/20075/30/20075/30/2007APART
DetailsForrest France
NW stair ceiling third floor fire sprinklers are approved for cover, also discussed flange hanger attatchments for the 4" main and trapeeze assemblies.
INSP-Sprinkler Rough-in5/29/20075/29/20075/29/2007PNR
DetailsForrest France
UG piping is completed, however thrust blocking is not installed at this time.
INSP-Sprinkler Rough-in5/2/20075/3/20075/3/2007APART
DetailsForrest France
OH FS is approved for cover as noted on stamped plan set.
INSP-Sprinkler Rough-in5/1/20075/2/20075/2/2007APART
DetailsForrest France
Overhead rough-in at the 1st and 2nd floor elevator lobby and restroom hard lids are good for cover as red lined on approved plans.