Permit Information
Permit NumberFIR07-00205
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 10136 S FEDERAL WAY
Project Nameoverhead MICRON NANOFAB
Customer Number 
ePlanReview 
Description
Install fire sprinklers through out this 112,315 ft/2 facility as required with exceptions in accordance with NFPA13. The fire sprinkler system work shall also comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. The Underground scope of work has been previously approved under permit FIR06-00940. The attached bldg. permit # is BLD06-03088 -- 11/06/07 Revised Scope of Work: These plans, material data sheets and hydraulic calculations were resubmitted As-Built with corrections made as a result of the denied plans and subsequent review comments from 09/18/2007. A summary of each plan modification made during construction has been clouded and referenced as Rev #2 dated 10/24/07 on sheets FP1 - FP10. That summary is attached to each copy of the final As-Built plans for the owners use.
Some modifications made during construction adversely affected the remote areas of operation resulting in the resubmittal of the plans and supporting calculations.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/28/200711/28/200711/28/2007PPASS
DetailsForrest France
Corrections verified for completion, fire sprinkler permit finaled.
INSP-Final Inspection11/26/200711/27/200711/28/2007PPART
DetailsForrest France
Reinspection for the cleanroom area defficiencies passed, also inspected first floor and mech. penthouse added and relocated heads due coverage issues.
INSP-Final Inspection11/13/200711/14/200711/15/2007AFAIL
DetailsForrest France
Noted several locations where heads are overspaced, blocked, or installed beyond listed spacing and max. allowable area.
INSP-Final Inspection11/12/200711/13/200711/13/2007PCANC
DetailsForrest France
Mike B is the contact, thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus
INSP-Final Inspection11/8/200711/9/200711/9/2007ACANC
DetailsForrest France
Mike B is the contact, thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus
INSP-Final Inspection8/30/20078/31/20078/31/2007PNR
DetailsForrest France
Missing as-built plans for verification of field mods.
INSP-Sprinkler Rough-in8/30/20078/31/20078/30/2007PCANC
DetailsForrest France
Please call 1/2hr prior to inspection. Mike B is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Final Inspection8/23/20078/27/20078/27/2007APART
DetailsForrest France
Project is not ready for final per contractor due to missing ceilings at several locations, need to complete final walk-through with provided as-built plans reflecting field modifications.
INSP-Sprinkler Rough-in7/16/20077/16/20077/16/2007APART
DetailsForrest France
See approved plan set for defficient areas.
INSP-Sprinkler Rough-in/Hydro7/12/20077/13/20077/13/2007APART
DetailsForrest France
OH hydrostatic testing completed acceptable, rough-in reinspect for the fan deck area failed due to missing hanger at added arm-over to a head beneath a duct at the NW corridor, also installed incorrect size rings at added branch line hangers in the fan attic 201D, stair #4 200Y is not complete at this time.
INSP-Sprinkler Rough-in7/5/20077/9/20077/9/2007PFAIL
DetailsForrest France
Reinspected defficient items on sheet FP8-completed okay. See sheet FP9 and 10 on approved plans for 3rd floor fan deck inspected today, red lined areas in need of correction including hangers, lacking coverage, seismic clearance at the riser main, blocked heads, retaining straps, etc.
INSP-Sprinkler Rough-in6/25/20076/26/20076/26/2007PFAIL
DetailsForrest France
Inspected OH rough-in for the 2nd level areas A and B sheets FP5 and 6, noted on plans defficient areas with missing heads, overspaced heads, hangers, retaining straps, areas not yet complete etc., flex heads in the cleanroom are not completed at this time.
INSP-Sprinkler Rough-in6/21/20076/22/20076/22/2007PFAIL
DetailsForrest France
Completed rough-in inspection for the basement subfab, process bay and chem. labs per sheet FP3, noted locations where head spacing, seismic bracing, and hangers need to be corrected, circled areas where install is not complete.