INSP-Final Inspection | 8/6/2008 | 8/8/2008 | 8/8/2008 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/5/2008 | 8/6/2008 | 8/6/2008 | P | CANC |
Troy Cobbley
|
|
|
Per Jim Danes the replacement sprinkler canopies are on order. The inspection will be called in at a later time.
|
INSP-Final Inspection | 8/5/2008 | 8/5/2008 | 8/5/2008 | P | FAIL |
Troy Cobbley
|
|
|
Need verification that the canopies have been factory painted. All other items are ok.
|
INSP-Final Inspection | 8/4/2008 | 8/5/2008 | 8/5/2008 | A | FAIL |
Troy Cobbley
|
|
|
Need verification that the canopies have been factory painted. All other items are ok.
|
INSP-Sprinkler Rough-in/Hydro | 6/19/2008 | 6/20/2008 | 6/20/2008 | A | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2008 | 5/22/2008 | 5/22/2008 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Sprinkler Rough-in | 4/30/2008 | 5/1/2008 | 5/1/2008 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Simplex to provide as-builts.
|
INSP-Sprinkler Rough-in | 2/15/2008 | 2/19/2008 | 2/19/2008 | A | PASS |
Troy Cobbley
|
|
|
The underground supply piping for building "A" is ok for cover
|
INSP-Sprinkler Rough-in/Hydro | 2/5/2008 | 2/6/2008 | 2/6/2008 | A | PASS |
Troy Cobbley
|
|
|
The sprinkler piping is ok to cover. Contractor provided Brian Johnson revised hydraulic calculations. The fire sprinkler contractor still needs to provide resubmittals for all of the changes that have occured prior to a final inspection for this project.
|