Permit Information
Permit NumberFIR07-00233
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 502 S 15TH ST
Project Name
Customer Number 
ePlanReview 
Description
Revised Scope of Work
To install a fire life safety NFPA 13R system to prevent flashover (total involvement) in the room of fire origin, where sprinklered, and to improve the chance for occupants to escape or be evacuated, in a new 6,400-ft/2 two story, apartment building. An NFPA 13R fire sprinkler protection system is required. The system shall be equipped a separate floor control valve for each floor, and an alarm initiating device connected to an alarm system and an outside annunciating devise. All fire sprinkler work and related, which includes dual service underground water supply, the system backflow prevention device (provided by others), shall be per NFPA 13R, approved plans, engineering/red-lining and attached review comments, under direction of the Fire Chief. This permit is attached to: BLD06-00074.08/09/07 Revised Scope of Work
In addition to the scope of work outlined in the 05/02/07 comments and the original scope as it was defined, the contractor has met code compliance by adding coverage at the exterior patios and canopy’s per IFC 903.3.1.2.1 To be field verified by a fire life safety inspector.
05/02/07 Scope of Work
To install a fire life safety NFPA 13R system to prevent flashover (total involvement) in the room of fire origin, where sprinklered, and to improve the chance for occupants to escape or be evacuated, in a new 6,400-ft/2 two story, apartment building. An NFPA 13R fire sprinkler protection system is required. The system shall be equipped a separate floor control valve for each floor, and an alarm initiating device connected to an alarm system and an outside annunciating devise. All fire sprinkler work and related, which includes dual service underground water supply, the system backflow prevention device (provided by others), shall be per NFPA 13R, approved plans, engineering/red-lining and attached review comments, under direction of the Fire Chief. This permit is attached to: BLD06-00074.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/20/20082/21/20082/21/2008APASS
DetailsForrest France
Fire sprinkler inspection comleted. KR
INSP-Sprinkler Rough-in11/26/200711/27/200711/27/2007APART
DetailsForrest France
UG fire supply line flush completed satisfactory.
INSP-Sprinkler Rough-in/Hydro11/16/200711/20/200711/20/2007APART
DetailsForrest France
UG supply line hydro test passed.
INSP-Sprinkler Rough-in8/22/20078/23/20078/23/2007APART
DetailsForrest France
UG fire supply line from the stub in at the foundation to the PIV only is okay for cover. Also inspected UG fire supply lines for the other three buildings not separately requested for inspection under respective FIR #'s as will be required for hydrostatic and flushing inspections.
INSP-Sprinkler Rough-in8/16/20078/17/20078/17/2007APART
DetailsForrest France
DSW head installation at the second floor unit balconies appears acceptable, need approved plans on site for verification at next scheduled inspection.
INSP-Sprinkler Rough-in8/15/20078/16/20078/16/2007PCANC
DetailsForrest France
Overbooked, no time available for this inspection today.
INSP-Sprinkler Rough-in/Hydro6/12/20076/13/20076/13/2007APASS
DetailsTroy Cobbley
The above ground hydro test of both risers passed.
INSP-Sprinkler Rough-in/Hydro6/11/20076/12/20076/12/2007AFAIL
DetailsForrest France
No hydrostatic test completed due to start pressures well below 200 psi., noted riser manifolds will need to be adjusted to provide access to the flow switches, recommend nailer plates be installed at 1.5" risers to the 2nd floor. C/N items from the previous inspection and tenting for the second floor are acceptable.
INSP-Sprinkler Rough-in/Hydro6/5/20076/7/20076/11/2007AFAIL
DetailsForrest France
Missing proper hangers at the FDC piping, one utility room pendent is missing a hanger, need correct temp. SW head at a first floor bedroom, piping at two locations adjacent to the 1st floor carports are subject to freeze potential as installed, missing head at the riser, overspaced heads at the 2nd floor in three units, need to verifiy tenting prior to approval for cover.