INSP-Final Inspection | 5/9/2007 | 5/10/2007 | 5/10/2007 | A | PASS |
Forrest France
|
|
|
Final FS permit inspection passed, corrections complete.
|
INSP-Final Inspection | 5/4/2007 | 5/7/2007 | 5/7/2007 | A | PART |
Forrest France
|
|
|
Pending ceiling tile, lockout at the air comp. switch as discussed.
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2007 | 5/3/2007 | 5/3/2007 | P | PART |
Forrest France
|
|
|
Air testing for the preaction system passed inspection.
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2007 | 5/2/2007 | 5/2/2007 | P | PART |
Forrest France
|
|
|
Begin air test 2:35 pm @ 52psi. as marked on guage.
|
INSP-Sprinkler Rough-in | 5/1/2007 | 5/2/2007 | 5/2/2007 | A | PART |
Forrest France
|
|
|
OH installation is acceptable, hydrostatic test of the preaction system completed, noted changes at preaction riser including drain termination point, different PRV than what is submitted, riser trim has been modified to include a potter ps40 in lieu of the mfg. supplied pressure switch.
|