Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR07-00285
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 2501 N BOGUS BASIN RD
Project NameHEALTHWISE
Customer Number 
ePlanReview 
Description
Original Scope of Work:
Install a wet pipe system to serve through out the new structure. The systems will consist of a wet preaction riser and an anti-freeze loop to serve the exterior canopy. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD06-02598 & UG permit #FIR07-00364.
Original Plan Review Comments:5th Plan Review Comments 08/16/07:
The plans were resubmitted due to modifications in the field. The modifications were apparent TI changes which exposed un-sprinklered areas. The modifications were made with-in the remote area of operation which adversely affected the calculations. This revision is noted to be Rev. # 3 dated 07/13/07. All changes are clouded and noted on sheets FP-1 & 2. Calc area #2 summary appears to be correct.5th Plan Review Comments 08/16/07:
1. The plans were resubmitted due to modifications in the field. The modifications were apparent TI changes which exposed un-sprinklered areas. The modifications were made with-in the remote area of operation which adversely affected the calculations. This revision is noted to be Rev. # 3 dated 07/13/07. All changes are clouded and noted on sheets FP-1 & 2. Calc area #2 summary appears to be correct.Original Scope of Work:
Install a wet pipe system to serve through out the new structure. The systems will consist of a wet preaction riser and an anti-freeze loop to serve the exterior canopy. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD06-02598 & UG permit #FIR07-00364.
10/15/07 6th Plan Review Comments:
1. These As-Built plans were resubmitted due to modifications in the field. The modification adversely affects remote area 2 which required a complete resubmittal. Four additional heads were installed to accommodate the modifications. The Anti-freeze loop expansion chamber has been moved to the exterior of the bldg. The revision is noted to be Rev. #4, dated 10/04/07 FP-2 of 2.

Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/16/200710/18/200710/18/2007APASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection10/12/200710/15/200710/15/2007PFAIL
DetailsForrest France
Provide forward flow bypass as indicated on approved plans, preaction pressure switch is not connected to the outside bell, need 911 sign at bell, provide lockout for the switches to the air compressor, need to certify the DCVA and the RP, provide calc. stickers, tags, signage etc. at the riser, need signage and locks for the control valves at the antifreeze loop, provide as-builts for field changes, need final walkthrough completed.
INSP-Sprinkler Rough-in9/20/20079/21/20079/21/2007APART
DetailsForrest France
Noted correction items from the previous inspection are complete, OH rough-in is acceptable.
INSP-Sprinkler Rough-in9/10/20079/11/20079/11/2007PFAIL
DetailsForrest France
See approved plans for areas in need of correction including overspacing at the data room, obstructed head at the second floor mech room, need to add one head in the riser room, blocked SW heads as noted, the antifreeze loop is not yet installed.
INSP-Sprinkler Rough-in/Hydro9/7/20079/10/20079/10/2007PPART
DetailsForrest France
OH hydrostatic test for the wet system and the preaction system both passed, contractor also completed a satisfactory UG supply line hydro as well.
INSP-Sprinkler Rough-in7/20/20077/23/20077/23/2007AFAIL
DetailsForrest France
Inspection for the 1st floor hard lid ceilings only, pendent head at the NW entry does not meet requirements of NFPA 13 table 8.6.5.1.2, heads at the restrooms and the elevator equip. room are okay for cover.
INSP-Supply line flush7/13/20077/16/20077/16/2007APART
DetailsForrest France
UG fire supply line flush completed satisfactory, circled on approved plans areas okay for cover on the 2nd floor, discussed coverage below stairs at the NW entry.
INSP-Sprinkler Rough-in7/11/20077/12/20077/12/2007APART
DetailsForrest France
Heads and piping at the 2nd floor stairway and restroom hard lid ceilings appears satisfactory, however no approved plans were made available on site for verification.