INSP-Final Inspection | 10/16/2007 | 10/18/2007 | 10/18/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 10/12/2007 | 10/15/2007 | 10/15/2007 | P | FAIL |
Forrest France
|
|
|
Provide forward flow bypass as indicated on approved plans, preaction pressure switch is not connected to the outside bell, need 911 sign at bell, provide lockout for the switches to the air compressor, need to certify the DCVA and the RP, provide calc. stickers, tags, signage etc. at the riser, need signage and locks for the control valves at the antifreeze loop, provide as-builts for field changes, need final walkthrough completed.
|
INSP-Sprinkler Rough-in | 9/20/2007 | 9/21/2007 | 9/21/2007 | A | PART |
Forrest France
|
|
|
Noted correction items from the previous inspection are complete, OH rough-in is acceptable.
|
INSP-Sprinkler Rough-in | 9/10/2007 | 9/11/2007 | 9/11/2007 | P | FAIL |
Forrest France
|
|
|
See approved plans for areas in need of correction including overspacing at the data room, obstructed head at the second floor mech room, need to add one head in the riser room, blocked SW heads as noted, the antifreeze loop is not yet installed.
|
INSP-Sprinkler Rough-in/Hydro | 9/7/2007 | 9/10/2007 | 9/10/2007 | P | PART |
Forrest France
|
|
|
OH hydrostatic test for the wet system and the preaction system both passed, contractor also completed a satisfactory UG supply line hydro as well.
|
INSP-Sprinkler Rough-in | 7/20/2007 | 7/23/2007 | 7/23/2007 | A | FAIL |
Forrest France
|
|
|
Inspection for the 1st floor hard lid ceilings only, pendent head at the NW entry does not meet requirements of NFPA 13 table 8.6.5.1.2, heads at the restrooms and the elevator equip. room are okay for cover.
|
INSP-Supply line flush | 7/13/2007 | 7/16/2007 | 7/16/2007 | A | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory, circled on approved plans areas okay for cover on the 2nd floor, discussed coverage below stairs at the NW entry.
|
INSP-Sprinkler Rough-in | 7/11/2007 | 7/12/2007 | 7/12/2007 | A | PART |
Forrest France
|
|
|
Heads and piping at the 2nd floor stairway and restroom hard lid ceilings appears satisfactory, however no approved plans were made available on site for verification.
|