INSP-Final Inspection | 11/7/2007 | 11/7/2007 | 11/7/2007 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 11/6/2007 | 11/7/2007 | 11/7/2007 | P | PART |
Forrest France
|
|
|
Hydrostatic testing of the preaction system piping completed per K. Roule.
|
INSP-Sprinkler Rough-in/Hydro | 11/6/2007 | 11/6/2007 | 11/6/2007 | P | PART |
Forrest France
|
|
|
Pneumatic testing for the preaction system passed within allowable pressure loss of 1 1/2 psig.
|
INSP-Final Inspection | 11/1/2007 | 11/5/2007 | 11/5/2007 | P | PART |
Forrest France
|
|
|
Begin 24hr. pneumatic testing of the preaction system at 41psi.@11:40am.
|
INSP-Sprinkler Rough-in/Hydro | 11/1/2007 | 11/5/2007 | 11/5/2007 | P | PART |
Forrest France
|
|
|
Fire sprinkler rough-in completed acceptable.
|