INSP-Final Inspection | 11/29/2007 | 11/30/2007 | 11/30/2007 | A | PASS |
Forrest France
|
|
|
Corrections verified, resubmittals for as-built plans accepted, final inspection passed. NFPA 72 record of completion forms to be delivered to PDS fire office today for signature as agreed.
|
INSP-Final Inspection | 10/25/2007 | 10/26/2007 | 10/26/2007 | A | PART |
Forrest France
|
|
|
Verified corrections have been completed, final pending resubmitted plans reflecting all field modifications.
|
INSP-Final Inspection | 10/25/2007 | 10/25/2007 | 10/25/2007 | P | NH |
Forrest France
|
|
|
No access available to the areas in need of inspection.
|
INSP-Final Inspection | 10/23/2007 | 10/23/2007 | 10/23/2007 | P | CANC |
Forrest France
|
|
|
Duplicate inspection request.
|
INSP-Final Inspection | 10/19/2007 | 10/22/2007 | 10/23/2007 | A | PART |
Forrest France
|
|
|
Tested cleanroom notification-noted two areas lacking sufficient visual coverage, need to program voltage monitoring at the elevator for a supervisory condition, retested c/n items from previous inspection.
|
INSP-Final Inspection | 10/18/2007 | 10/19/2007 | 10/19/2007 | A | PART |
Forrest France
|
|
|
Elevator testing completed, noted voltage monitoring to be supervisory, not an alarm condition as programed.
|
INSP-Alarm Testing | 10/5/2007 | 10/9/2007 | 10/9/2007 | A | DEFR |
Forrest France
|
|
|
sandy Note:elevator Phone #: ###-#### Can be completed in conjunction with the remainder of the fire alarm work to be inspected ie. cleanroom areas.
|
INSP-Alarm Testing | 9/11/2007 | 9/11/2007 | 9/11/2007 | A | PART |
Forrest France
|
|
|
Tested units at the fan deck, some items on this level are not yet amended for reinspection, the horn at the roof level sheet FA 2.4 does not function, notification devices at the underfloor area tested acceptable, EOL at the office area retested okay after corrections. Noted fire alarm for the office area is now approved.
|
INSP-Alarm Testing | 9/11/2007 | 9/12/2007 | 9/11/2007 | A | CANC |
Forrest France
|
|
|
Scheduled by a contractor via Hello! on 9/11/2007 at 7:10:04 AM. Contact: ###-####. Inspection cancelled from web by: Patricia Smith
|
INSP-Final Inspection | 9/7/2007 | 9/10/2007 | 9/10/2007 | A | PART |
Forrest France
|
|
|
Tested second floor fan deck areas, noted one SD in the electrical room to be added, two duct detectors are descripted incorrect, marked devices not yet ready for testing including the elevator and four duct detectors at units not currently running, discussed occupancy requirements with the general contractor for the office portion of the first floor.
|
INSP-Alarm Testing | 9/5/2007 | 9/7/2007 | 9/10/2007 | A | PART |
Forrest France
|
|
|
EOL voltage drop at the office area is too low, one SD in the electrical room has an incorrect descriptor, incorrect cd at the receiving area amended while on site, retested noted defficiencies from the previous visit, highlighted locations on the first floor not yet complete for inspection including the elevator and cleanroom areas, noted ECS room staff is lacking for constant attendance as only one trained employee is provided at this time.
|
INSP-Alarm Testing | 9/5/2007 | 9/6/2007 | 9/7/2007 | A | PART |
Forrest France
|
|
|
Reinspection for the first floor office area defficiencies, see approved plan set for locations tested today and items in need of correction including blocked strobe notification, incorrect descriptor at an electrical room smoke, SD at an electrical closet, noted ECS room is now staffed with trained personel.
|
INSP-Final Inspection | 8/31/2007 | 9/5/2007 | 9/6/2007 | A | PART |
Forrest France
|
|
|
Retested noted defficiencies at the basement level, see approved plans for first floor areas tested today, noted descriptor for the electrical room 101G reports a 101N, will need to retest one SD at the east corridor door hold release.
|
INSP-Final Inspection | 8/31/2007 | 9/4/2007 | 9/4/2007 | A | NR |
Forrest France
|
|
|
sandy; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt
|
INSP-Final Inspection | 8/29/2007 | 8/30/2007 | 8/30/2007 | A | FAIL |
Forrest France
|
|
|
See approved plans sheet FA1 for defficiencies at the south office area inspected today including several blocked horn/strobe notification devices at the open office 105 due to 80" high cubicle partitions, SD at the nac panels in the BCS room is too close to an air return grill, one blocked h/s at the file room due to cabinetry, one overspaced h/s at the west side of office 105, noted the ECS room is not staffed at this time and missing some required items per NFPA 72 ch. 8.
|
INSP-Final Inspection | 8/28/2007 | 8/29/2007 | 8/29/2007 | P | CANC |
Troy Cobbley
|
|
|
sandy Phone #: ###-####Due to the abundance of inspections today there was not adequate time to perform this one. It will need to be rescheduled.
|
INSP-Final Inspection | 8/27/2007 | 8/28/2007 | 8/28/2007 | A | FAIL |
Forrest France
|
|
|
Tested remainder of devices on sheet FP2.1, noted locations on plan in need of correction including non-functional a/v devices, incorrect cd settings, blocked a/v, noted six duct detectors with the sample and vent tubes switched- need to install per mfg. recommendations or provide air flow test data.
|
INSP-Alarm Testing | 8/21/2007 | 8/27/2007 | 8/27/2007 | A | FAIL |
Forrest France
|
|
|
See approved plans for areas inspected today, noted one H/S is blocked, one incorrect cd rating, switched address on the sprinkler PIV and forward flow tampers.
|