INSP-Final Inspection | 11/13/2007 | 11/13/2007 | 11/13/2007 | P | PASS |
Forrest France
|
|
|
Connection to fire alarm was complete.
|
INSP-Sprinkler Rough-in | 9/4/2007 | 9/5/2007 | 9/5/2007 | A | PART |
Forrest France
|
|
|
OH rough-in is approved for cover, noted items from the previous inspection have been completed.
|
INSP-Sprinkler Rough-in | 8/28/2007 | 8/28/2007 | 8/28/2007 | P | FAIL |
Forrest France
|
|
|
Provide sprinkler coverage at the second floor dormer concealed space or fill entirely with insulation, provide matching temp. sprinkler heads under the stairs at the first floor, two uprights at the attic are blocked by insulation.
|
INSP-Sprinkler Rough-in | 8/23/2007 | 8/24/2007 | 8/24/2007 | P | FAIL |
Forrest France
|
|
|
Insulation at the roof deck is still obstructing upright head coverage, also missing cold cavity protection at the concealed spaces above the riser and lobby.
|
INSP-Sprinkler Rough-in/Hydro | 8/20/2007 | 8/21/2007 | 8/21/2007 | P | PART |
Forrest France
|
|
|
AG hydrostatic test passed, verified resubmitted plans on site, overhead is NOT approved for cover at this time due to upright head obstructions by insulation at the deck, also missing cold cavity protection for piping above the riser room and reception area.
|
INSP-Sprinkler Rough-in/Hydro | 7/18/2007 | 7/19/2007 | 7/19/2007 | P | PART |
Troy Cobbley
|
|
|
Underground hydro test passed but the overhead would not hold pressure.
|
INSP-Sprinkler Rough-in/Hydro | 7/17/2007 | 7/18/2007 | 7/18/2007 | A | FAIL |
Troy Cobbley
|
|
|
The overhead piping located on the second floor has numerous changes. These changes match the installation drawings but these drawings have no city approval. Resubmittals will be required showing the changes. All of these changes are in the remote area on the second floor. Insulation will need to be installed in the unsprinklered concealed spaces prior to cover approval as well.
|
INSP-Sprinkler Rough-in/Hydro | 7/17/2007 | 7/17/2007 | 7/17/2007 | P | DEFR |
Forrest France
|
|
|
Scheduled 7/18
|
INSP-Supply line flush | 7/9/2007 | 7/10/2007 | 7/10/2007 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory, hydrostatic test not ready due to pressure loss at the guage.
|
INSP-Sprinkler Rough-in | 6/14/2007 | 6/15/2007 | 6/15/2007 | P | PART |
Forrest France
|
|
|
UG fire supply line is approved for cover.
|