Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR07-00474
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 950 W BANNOCK ST Unit: 700
Project Name10TH & BANNOCK
Customer Number 
ePlanReview 
Description
Modify the existing system by adding a 1.5” pre-action system (Double Interlock) to server the Data Room. Additional work includes adding and relocating heads to accommodate a new wall and ceiling layout. This work is limited to the 7th floor.
The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD07-01043.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/27/20078/27/20078/28/2007PPASS
DetailsForrest France
Corrections are complete, fire sprinkler permit finaled.
INSP-Final Inspection8/27/20078/27/20078/27/2007PFAIL
DetailsForrest France
Corrections are not complete, one head location is overspaced from an adjacent wall.
INSP-Final Inspection8/24/20078/24/20078/24/2007PFAIL
DetailsForrest France
Overspaced heads at four locations.
INSP-Final Inspection8/23/20078/23/20078/23/2007PFAIL
DetailsForrest France
Work is not complete.
INSP-Final Inspection8/22/20078/22/20078/23/2007PDEFR
DetailsForrest France
Rescheduled for 8/23.
INSP-Final Inspection8/17/20078/20/20078/20/2007APART
DetailsForrest France
Functional testing of the preaction system only, remainder of OH work is not ready for final inspection.
INSP-Final Inspection8/15/20078/16/20078/16/2007AFAIL
DetailsForrest France
Scope of work is not yet complete, the preaction riser failed to function properly.
INSP-Final Inspection8/14/20078/15/20078/15/2007ANR
DetailsForrest France
Project is not ready for final inspection at this time.
INSP-Sprinkler Rough-in/Hydro8/13/20078/14/20078/14/2007PPART
DetailsForrest France
24 hr pneumatic test for the preaction system passed.
INSP-Final Inspection8/10/20078/13/20078/13/2007PPART
DetailsForrest France
Begin air test at 3:30@ 49psig.
INSP-Sprinkler Rough-in/Hydro8/9/20078/10/20078/10/2007PFAIL
DetailsForrest France
Pneumatic testing failed due to 3 1/2 psi pressure loss at the guage.
INSP-Sprinkler Rough-in8/9/20078/9/20078/9/2007PPART
DetailsForrest France
Begin 24 hr air testing at 45 psi.@4:00 pm.