INSP-Final Inspection | 9/19/2007 | 9/20/2007 | 9/20/2007 | A | PASS |
Forrest France
|
|
|
Noted items at the previous inspection have been verified for completion, fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 9/5/2007 | 9/6/2007 | 9/6/2007 | A | PART |
Forrest France
|
|
|
OH hydrostatic test passed. No occupancy is allowed prior to the issuance of a certificate of occupancy for the building per conditon of the issued project permits.
|
INSP-Final Inspection | 9/4/2007 | 9/5/2007 | 9/5/2007 | A | NR |
Forrest France
|
|
|
Project is not ready for inspection, OH was not pressurized for a hydrostatic test at the time of site visit, rescheduled per conversation with contractor, also need to provide approved resubmittals prior to final. NOTE: contacted the general contractor regarding no occupany prior to the issuance of a CO.
|
INSP-Sprinkler Rough-in/Hydro | 8/29/2007 | 8/30/2007 | 8/30/2007 | A | CANC |
Forrest France
|
|
|
Overbooked
|
INSP-Sprinkler Rough-in/Hydro | 8/28/2007 | 8/29/2007 | 8/29/2007 | P | CANC |
Troy Cobbley
|
|
|
Due to the abundance of inspections today there was not adequate time to perform this one. It will need to be rescheduled.
|
INSP-Sprinkler Rough-in | 7/19/2007 | 7/20/2007 | 7/20/2007 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the location where the sprinkler piping can be covered by the hard lids.
|