INSP-Final Inspection | 11/16/2007 | 11/19/2007 | 11/19/2007 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 11/16/2007 | 11/16/2007 | 11/16/2007 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled, contractor to provide SW heads at the head box as agreed.
|
INSP-Sprinkler Rough-in/Hydro | 11/6/2007 | 11/7/2007 | 11/7/2007 | A | PART |
Forrest France
|
|
|
OH hydrostatic test passed, c/n items from the previous inspection have been completed, noted that no provision has been made at the riser for forward flow testing of the DCVA backflow.
|
INSP-Sprinkler Rough-in | 9/5/2007 | 9/6/2007 | 9/6/2007 | A | PART |
Forrest France
|
|
|
OH rough-in is approved except as noted or not yet complete-see annotations on stamped plan set including seismic clearance at a 4" riser, overspaced heads due to HVAC, missing head at the janitors room, SW at the overhead doors are not installed at this time.
|
INSP-Supply line flush | 8/28/2007 | 8/29/2007 | 8/29/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground supply flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/28/2007 | 8/29/2007 | 8/29/2007 | A | PASS |
Troy Cobbley
|
|
|
The underground hydro test passed.
|
INSP-Sprinkler Rough-in | 7/24/2007 | 7/25/2007 | 7/25/2007 | A | PART |
Forrest France
|
|
|
UG fire supply line installation is good for cover.
|