INSP-Final Inspection | 11/29/2007 | 11/30/2007 | 11/30/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled. The light fixtures have been changed to can lights which no longer are obstructions.
|
INSP-Supply line flush | 11/21/2007 | 11/26/2007 | 11/26/2007 | A | PASS |
Troy Cobbley
|
|
|
The hydro tests of the underground and both overhead systems passed. The underground flush passed as well.
|
INSP-Final Inspection | 11/19/2007 | 11/20/2007 | 11/20/2007 | P | FAIL |
Troy Cobbley
|
|
|
Sprinkler pendants are blocked by light fixtures. Both overhead and underground piping need hydro tested. The underground needs flushed. All riser details need inspected. Alarm interconnections need to be tested.
|
INSP-Sprinkler Rough-in | 8/27/2007 | 8/28/2007 | 8/28/2007 | A | FAIL |
Troy Cobbley
|
|
|
The sprinkler rough-in is ok but there have been alot of 90's added into the branchlines and the 1 1/2" main due to vaulted ceilings in each of the apartments. Also no tenting has been done. The sprinkler piping is not to be covered and resubmittals with hydraulic calculations are required prior to cover.
|
INSP-Sprinkler Rough-in | 8/20/2007 | 8/21/2007 | 8/21/2007 | A | PASS |
Troy Cobbley
|
|
|
First floor piping is ok to cover. This is the only area inspected. There were some minor changes and per the installer as-builts are being resubmitted to the city.
|
INSP-Sprinkler Rough-in | 7/26/2007 | 7/30/2007 | 7/30/2007 | A | PART |
Forrest France
|
|
|
UG fire supply line is approved for cover, depth of bury is okay provided infill meets grade at existing landscaping on either side, also need to provide method for seismic clearance where the riser passes through the floor slab.
|